Cement and Sand for 1 m² of 12 mm Plaster (1:4 and 1:6 Mix)

Brick wall half covered with 12 mm cement plaster and a trowel

For 1 m² of 12 mm thick cement plaster, a 1:4 mix needs about 4.39 kg of cement and 0.0122 m³ (0.43 cft) of sand. A 1:6 mix needs about 3.14 kg of cement and 0.0131 m³ (0.46 cft) of sand.

Per 100 sq ft of wall, that is about 0.82 bag of cement for 1:4 and 0.58 bag for 1:6. The working below uses a dry volume factor of 1.27 and cement at 1440 kg/m³.

Cement and sand for 12 mm plaster: step by step

  1. Wet volume = area × thickness = 1 × 0.012 = 0.012 m³.
  2. Dry volume = 0.012 × 1.27 = 0.01524 m³. The factor allows for the loss in volume when water is added to dry cement and sand, since fine particles settle into the gaps.
  3. 1:4 mix (sum 5): cement = 0.01524 ÷ 5 = 0.003048 m³ × 1440 = 4.39 kg. Sand = 0.01524 × 4 ÷ 5 = 0.0122 m³.
  4. 1:6 mix (sum 7): cement = 0.01524 ÷ 7 = 0.002177 m³ × 1440 = 3.14 kg. Sand = 0.01524 × 6 ÷ 7 = 0.0131 m³.
1 m² × 0.012 m = 0.012 m³ wet × 1.27 = 0.01524 m³ dry 1:4 (divide by 5) Cement 0.003048 m³ = 4.39 kg Sand 0.0122 m³ = 0.43 cft 1:6 (divide by 7) Cement 0.002177 m³ = 3.14 kg Sand 0.0131 m³ = 0.46 cft Cement density 1440 kg/m³, 1 bag = 50 kg
From plaster area to cement and sand for 1 m² of 12 mm plaster.

Quantities per m², per 100 sq ft and per 100 m²

Area (12 mm plaster)1:4 cement1:4 sand1:6 cement1:6 sand
1 m²4.39 kg (0.088 bag)0.0122 m³ / 0.43 cft3.14 kg (0.063 bag)0.0131 m³ / 0.46 cft
100 sq ft (9.29 m²)40.8 kg (0.82 bag)0.113 m³ / 4.00 cft29.1 kg (0.58 bag)0.121 m³ / 4.29 cft
100 m²438.9 kg (8.78 bags)1.22 m³ / 43.1 cft313.5 kg (6.27 bags)1.31 m³ / 46.1 cft

1:4 is common for ceilings, outer walls and wet areas. 1:6 is common for inside brick walls. Your drawings or specification decide the mix.

The 1.3 plus wastage approach

Many site estimators use a dry factor of about 1.3 and then add around 5% for wastage. That gives 1.3 × 1.05 = 1.365, which is about 7.5% more material than the 1.27 figure. For 100 m² of 12 mm plaster this means about 9.43 bags of cement in 1:4 and 6.74 bags in 1:6.

Some textbooks go further: they first add 20% to the wet volume for filling joints and uneven surfaces, then apply 1.27. That is 1.2 × 1.27 = 1.524 overall, or about 10.53 bags in 1:4 per 100 m². Each method is in use, so pick one and stay consistent across the estimate.

Worked example

Inside walls of a room have 400 sq ft of plaster area after deducting doors and windows, in 1:6. Cement = 4 × 0.58 = about 2.33 bags. Sand = 4 × 4.29 = about 17.1 cft.

The plaster calculator does this for any area, thickness and mix. For painting the same walls, see the paint calculator.

Cement and sand per m² for other thicknesses and mixes

The same method (wet volume x 1.27, cement at 1440 kg/m³) gives these figures per m² of plaster, before wastage. Read across for the mix you are using.

Thickness1:3 cement kg / sand m³1:41:51:6
6 mm2.74 / 0.00572.19 / 0.00611.83 / 0.00641.57 / 0.0065
10 mm4.57 / 0.00953.66 / 0.01023.05 / 0.01062.61 / 0.0109
12 mm5.49 / 0.01144.39 / 0.01223.66 / 0.01273.14 / 0.0131
15 mm6.86 / 0.01435.49 / 0.01524.57 / 0.01593.92 / 0.0163
20 mm9.14 / 0.01917.32 / 0.02036.10 / 0.02125.23 / 0.0218

How much wall one bag covers

On site it is often easier to think per bag. One 50 kg bag of cement in 12 mm plaster covers:

MixArea per bagSand per bag
1:39.1 m² (98 sq ft)0.104 m³ (3.7 cft)
1:411.4 m² (123 sq ft)0.139 m³ (4.9 cft)
1:513.7 m² (147 sq ft)0.174 m³ (6.1 cft)
1:615.9 m² (171 sq ft)0.208 m³ (7.4 cft)

If a mason uses a bag of 1:6 mortar and covers only about 12 m² of 12 mm plaster, either the wall is uneven and the plaster is going on thicker, or mortar is being wasted. That is a quick daily check for an owner.

Worked example: one bedroom, walls and ceiling

A bedroom 3.27 m x 3.77 m inside, with 2.875 m clear height. After the opening deductions explained in the whole-house plaster guide, the inside wall area is 38.63 m² and the ceiling is 12.33 m².

  • Walls, 12 mm in 1:6: cement 38.63 x 3.14 = 121.1 kg = 2.42 bags. Sand 38.63 x 0.0131 = 0.505 m³ = 17.8 cft.
  • Ceiling, 12 mm in 1:4: cement 12.33 x 4.39 = 54.1 kg = 1.08 bags. Sand 12.33 x 0.0122 = 0.150 m³ = 5.3 cft.
  • Total: about 3.5 bags of cement and 23 cft of sand; buy 4 bags and 25 cft with about 5% wastage.

Cost check. The Suryabinayak Municipality rate analysis 2081/82 gives Rs 452.42 per m² for 12.5 mm plaster in 1:6 and Rs 472.19 for 1:4 (materials, labour and 15% overhead). For this room: 38.63 x 452.42 = Rs 17,477 for the walls and 12.33 x 472.19 = Rs 5,822 for the ceiling, about Rs 23,300 in all. Rates differ by municipality and year, so use your own local rate.

Worked example: compound wall, both faces

A 30 m long, 1.8 m high compound wall plastered on both faces with 15 mm of 1:4 (outside work is usually thicker and richer): area = 30 x 1.8 x 2 = 108 m². Cement = 108 x 5.49 = 593 kg = 11.9 bags. Sand = 108 x 0.0152 = 1.65 m³ = 58 cft. Add the top of the wall if it is plastered too.

Common mistakes with plaster quantities

  • Estimating at 12 mm but plastering at 15 mm. Uneven brickwork pushes the average thickness up. 15 mm instead of 12 mm uses 25% more cement and sand. Straighten bad brickwork before plastering, not with plaster.
  • Using unscreened sand. Silt and clay in sand weaken plaster and cause cracks; screen it and keep it clean.
  • Mixing more than can be used. Mortar that starts to set before it is applied should be thrown away, not re-mixed with water.
  • Forgetting the ceiling and the outside. Room-by-room wall figures miss the ceiling, parapets, sunshades and the outside face, which together can be more than half of a house's plaster.
  • Skipping curing. Plaster that dries too fast cracks. Keep it damp for several days after it sets, the same way you cure concrete. To size the job for any room, use the plaster calculator.

Frequently asked questions

What about 20 mm outside plaster?

Scale by thickness. 20 mm in 1:6 needs 20 ÷ 12 times the 12 mm amount, which is about 0.97 bag of cement and 7.14 cft of sand per 100 sq ft.

Why is sand more in 1:6 than in 1:4?

The dry volume is the same, so a leaner mix has more of that volume as sand and less as cement.

Does this include wastage?

No. The 1.27 factor only converts wet volume to dry volume. Add wastage, often around 5%, or use the 1.3 plus wastage method above. Rough brickwork and uneven walls need more.

Preparing for the NEC licence or Lok Sewa?Practise 2,100+ civil engineering MCQs with answers, free.Start practising

Comments

Need a calculator we don’t have yet?

Tell us what you use on site or in class. The most requested tools get built next.