Plaster Quantity for a Whole House in Nepal: Cement and Sand

Plaster quantity for a whole house in Nepal: wall and ceiling plaster area, cement bags and sand

To find the plaster quantity for a whole house, measure the plastered surface in square metres (outside walls, inside walls and ceilings separately), deduct openings by the IS 1200 rules, then multiply each area by its thickness and the dry factor 1.27 to get cement and sand. For the two-storey, 12-column house used in our earlier posts, that gives about 823 m² of plaster, 82 bags of cement and 12.9 m³ (455 cft) of sand before wastage. The steps, rules and tables below let you repeat this for your own drawing.

This post follows on from brick wall quantity for a house, which uses the same building, and from cement and sand for 1 m² of 12 mm plaster, which explains where the per m² figures come from.

What you need before you start

  • The floor plans with wall thickness, column size and room sizes.
  • The section: floor-to-floor height, slab thickness, plinth height above ground and parapet height.
  • The door and window schedule (sizes and numbers).
  • The plaster specification: mix and thickness for outside walls, inside walls and ceilings. Typical Nepali specifications are 20 mm in 1:4 outside, 12 mm in 1:6 inside and 12 mm in 1:4 on ceilings, but your drawings decide.

Plaster thickness and mix used on Nepali houses

IS 1661, the Indian code most Nepali specifications follow for cement plaster, describes a single coat of about 12 mm on inside walls, two coats of about 15 to 20 mm on outside walls, and a thin coat of about 6 mm on ceilings. Mixes from 1:4 to 1:6 cement to sand are common. In practice many house builders in Nepal put 12 mm on ceilings as well, because slab soffits are rarely flat enough for 6 mm. Keep each combination of thickness and mix as a separate item, because they use different amounts of cement.

Plaster (per 100 m²)Cement (50 kg bags)Sand (m³)Sand (cft)
6 mm, 1:4 (ceiling)4.390.6121.5
12 mm, 1:48.781.2243.1
12 mm, 1:66.271.3146.1
15 mm, 1:410.971.5253.8
15 mm, 1:67.841.6357.7
20 mm, 1:414.632.0371.8
20 mm, 1:610.452.1876.9

Basis: dry volume = area × thickness × 1.27, cement at 1,440 kg/m³, 50 kg bags, no wastage. Multiply by your area in m² and divide by 100.

How to measure plaster area: the IS 1200 deduction rules

Plaster is measured in m² of finished surface. IS 1200 Part 12 (method of measurement of plastering) sets out what to deduct for openings, and most Nepali estimates and municipal bills follow it. Clause 3.8 gives three size bands:

  • Openings up to 0.5 m² each: no deduction, and nothing is added for the jambs, sills and soffits. Ends of beams, joists and posts are not deducted either. A 0.6 × 0.6 m toilet ventilator (0.36 m²) falls here.
  • Openings over 0.5 m² and up to 3 m²: if both faces get the same plaster, deduct the opening from one face only. If the two faces get different plaster, deduct it from the face where the reveal is narrower; if the reveals are equal, deduct 50% of the opening on each face. Jambs and sills are not added. Most doors and windows in a house are in this band (a 1.5 × 1.2 m window is 1.8 m², a 0.9 × 2.1 m door is 1.89 m²).
  • Openings over 3 m² each: deduct the opening on each face, and measure the jambs, soffit and sill as plaster.

The idea is simple. For a mid-size opening, the plaster saved on the opening is roughly balanced by the extra work on the reveals around it, so the code deducts it only once. For a large opening the reveals are measured instead.

Plaster deductions for openings (IS 1200 Part 12, cl. 3.8) beam / slab soffit 0.36 m² 1.5 × 1.2 = 1.8 m² 2.4 × 2.1 = 5.04 m² jambs and soffit added Up to 0.5 m² No deduction, no reveals added 0.5 to 3 m² Same plaster both faces: deduct one face Different plaster, equal reveals: 50% each face Over 3 m² Deduct on each face, add jambs, soffit and sill Net plaster = face length × height − deductions (m²)
How IS 1200 Part 12 treats openings of different sizes when measuring plaster. Most house doors and windows fall in the middle band.

Step-by-step method for a whole house

  1. Split the work into items. Outside walls (including the parapet), inside walls, and ceilings. If toilets and the kitchen will be tiled to full height, leave those wall faces out of the plaster item; the tile bedding is a separate item.
  2. Outside walls. Take the outer perimeter of the building and multiply by the height from ground (or the top of the plinth finish) to the top of the parapet. The plaster runs over columns, beams and slab edges, so do not subtract them.
  3. Parapet. Add the inner face of the parapet (inner perimeter × parapet height) and the top, unless the top gets a separate concrete coping.
  4. Inside walls, floor by floor. Add the inside perimeter of the outer walls and both faces of every internal wall, then multiply by the clear height from floor to the slab soffit.
  5. Ceilings. Take the room areas at slab level. Add the sides and soffits of any beams that hang below the slab away from walls.
  6. Deduct openings by the three size bands above. Doing it room by room, an easy way to apply the 0.5 to 3 m² rule is to deduct half of each such opening in each room on either side. The total comes out the same as deducting one face.
  7. Convert to materials with the table above, add wastage (about 5% is common, more on rough brickwork) and round up to whole bags.

Worked example 1: one bedroom

A bedroom has column grid 3.5 × 4.0 m with 230 mm walls, so the inside size is 3.27 × 3.77 m. Floor-to-floor height is 3.0 m and the slab is 125 mm, so the clear height is 2.875 m. It has one 0.9 × 2.1 m door to the corridor, one 1.5 × 1.2 m window on an outside wall and one 0.6 × 0.6 m ventilator. Walls are 12 mm in 1:6 and the ceiling is 12 mm in 1:4.

LineWorkingResult
Wall perimeter2 × (3.27 + 3.77)14.08 m
Gross wall area14.08 × 2.87540.48 m²
Door (1.89 m², 0.5 to 3 band)half deducted in this room− 0.945 m²
Window (1.80 m², 0.5 to 3 band)half deducted on this face− 0.90 m²
Ventilator (0.36 m²)up to 0.5 m², no deduction0
Net wall plaster38.63 m²
Cement, walls (1:6)38.63 × 3.14 kg121 kg = 2.42 bags
Sand, walls38.63 × 0.01306 m³0.505 m³ = 17.8 cft
Ceiling area3.27 × 3.7712.33 m²
Cement, ceiling (1:4)12.33 × 4.39 kg54 kg = 1.08 bags
Sand, ceiling12.33 × 0.01219 m³0.150 m³ = 5.3 cft

If you deduct every opening in full, as many quick estimates do, the net wall area comes to 36.43 m², which is 2.2 m² (about 6%) less than the IS 1200 figure. On a whole house that gap grows to tens of square metres, as the next example shows.

Worked example 2: a two-storey, 12-column house

This is the same house as in our beam and brick wall posts: a 3 × 4 column grid with bays 3.5 + 4.0 m one way and 3.0 + 3.6 + 4.2 m the other, 350 mm columns, outer size 7.85 × 11.15 m, two storeys of 3.0 m, 125 mm slabs, 230 mm outer walls, 16.0 m of 115 mm internal walls per floor and a 1.0 m parapet. We take the plinth as 0.45 m above ground (an example value). Each floor has one 1.0 × 2.1 m outside door, five 1.5 × 1.2 m windows, two 0.6 × 0.6 m ventilators, five 0.9 × 2.1 m and two 0.75 × 2.1 m internal doors.

Outside plaster: 20 mm, 1:4

  • Outer perimeter = 2 × (7.85 + 11.15) = 38.00 m.
  • Height from ground to parapet top = 0.45 + 2 × 3.0 + 1.0 = 7.45 m, so gross area = 38.00 × 7.45 = 283.10 m².
  • Openings: the outside and inside faces get different plaster, and with frames set in the middle of the wall the reveals are equal, so 50% of each door and window comes off this face. Per floor: 0.5 × 2.1 + 5 × 0.5 × 1.8 = 5.55 m², so 11.10 m² for two floors. Ventilators are under 0.5 m², so no deduction.
  • Net walls = 283.10 − 11.10 = 272.00 m².
  • Parapet inner face = (38.00 − 8 × 0.115) × 1.0 = 37.08 m². Parapet top = 37.54 m centre line × 0.115 = 4.32 m².
  • Total outside plaster = 272.00 + 37.08 + 4.32 = 313.40 m².

Inside wall plaster: 12 mm, 1:6

  • Inside perimeter of the outer walls = 2 × (7.39 + 10.69) = 36.16 m. Both faces of internal walls = 2 × 16.0 = 32.00 m. Total face length = 68.16 m per floor.
  • Clear height = 3.0 − 0.125 = 2.875 m, so gross = 68.16 × 2.875 = 195.96 m² per floor.
  • Outer wall openings, inside face (50%): 5.55 m². Internal doors have the same plaster on both faces, so deduct one face only: 5 × 1.89 + 2 × 1.575 = 12.60 m². Total 18.15 m².
  • Net = 195.96 − 18.15 = 177.81 m² per floor, so 355.62 m² for two floors.

Column faces that project into rooms add a little more (each 350 mm column in a 230 mm wall sticks out about 120 mm), and so do beam sides below the slab. They are left out here to keep the example readable; add them from your plan if you want a tighter figure.

Ceiling plaster: 12 mm, 1:4

  • Inside area = 7.39 × 10.69 = 79.00 m², less internal wall footprint 16.0 × 0.115 = 1.84 m², so 77.16 m² per floor and 154.32 m² for two floors (the ground floor ceiling and the roof slab soffit).

Totals

ItemArea (m²)Cement (bags)Sand (m³)Sand (cft)
Outside walls and parapet, 20 mm 1:4313.4045.856.37224.9
Inside walls, 12 mm 1:6355.6222.304.65164.1
Ceilings, 12 mm 1:4154.3213.551.8866.4
Total823.3481.712.90455.4
With 5% wastage85.8 (order 86)13.54478

A quick check: the built-up area is 2 × 7.85 × 11.15 = 175.1 m², so this house has about 4.7 m² of plaster per m² of floor. If your own estimate is far from that for a similar house, look again at the heights and the internal wall lengths.

If the ceilings were 6 mm instead of 12 mm, ceiling cement would drop from 13.55 to 6.77 bags and sand from 1.88 to 0.94 m³. That is why the thickness belongs in the specification and the contract, not left to the mason.

What full deduction would have done

Deducting every opening in full on both faces (including ventilators) gives 74.04 m² of deductions on the inside walls instead of 36.30, and 23.64 m² on the outside instead of 11.10. The total area would drop by about 50 m², or roughly 6%. That matters when you check a contractor's bill measured by IS 1200, or when your material order falls short in the last week of plastering.

Cost estimate using a municipal rate

Municipal rate analyses give a rate per m² that already covers cement, sand, labour and scaffolding. The Suryabinayak Municipality rate analysis for 2081/82 lists these rates with 15% contractor overhead:

Item (Suryabinayak 2081/82)Rate (Rs/m²)Area in example 2 (m²)Amount (Rs)
20 mm, 1:4599.84313.401,87,988
12.5 mm, 1:6452.42355.621,60,890
12.5 mm, 1:4 (used for ceilings)472.19154.3272,868
Total823.344,21,745

The same document lists 12.5 mm in 1:3 at Rs 563.55, 20 mm in 1:3 at Rs 613.70 and 20 mm in 1:6 at Rs 568.74 per m². It does not give a separate ceiling rate, and ceiling work is slower, so labour-only quotes for ceilings are often higher. Rates change every fiscal year and differ between municipalities and districts, so use your own municipality's current rate analysis or local contractor quotes for a real budget. For the whole building budget, see the house construction cost calculator.

Plastered and painted houses next to bare brick houses along the Bishnumati river in Kathmandu
Plastered and painted houses beside unplastered brick ones in Kathmandu. Photo: Houses along the Vishnumati river - Kathmandu, Nepal by Sergey Ashmarin, CC BY-SA 3.0, via Wikimedia Commons (cropped).

Common mistakes seen on Nepali sites

  • Using the brick wall area for plaster. The brickwork area excludes columns, beams and lintels, but plaster covers them. In example 2 the brick area of the outer walls is about 148 m² for two floors, while the outside plaster is 313 m² because it runs over the frame, the plinth and the parapet.
  • Counting internal walls once. An internal wall is plastered on both faces. Measure it twice.
  • Deducting every opening on both faces. This undercounts by around 5 to 6% on a typical house. Follow the IS 1200 bands, or at least state clearly which rule your estimate uses.
  • Forgetting the parapet, the stair hall and the headroom (mumty). These are plastered on both sides and are easy to miss when you work floor by floor.
  • Mixing thicknesses in one item. 20 mm outside plaster uses about 67% more cement per m² than 12 mm in the same mix. Keep them separate.
  • Thick plaster to hide poor work. Walls out of plumb or columns out of line get filled with 25 to 40 mm of plaster. That costs cement and can crack. Check line and level before plastering, not after.
  • Short curing. Cement plaster should be kept damp for about 7 days. Plaster that dries in the sun on the second day cracks and sounds hollow when tapped.

Frequently asked questions

How many bags of cement are needed to plaster a 2-storey house in Nepal?

For the 175 m² two-storey house in example 2, about 82 bags without wastage and 86 with 5%. Your number depends on wall lengths, heights, thickness and mix. A rough check is about 0.47 to 0.49 bag per m² of built-up area for the specification used here.

Is plaster measured in m² or m³?

In m² of finished surface, with the thickness and mix stated in the item description. The m³ only appears when you convert to cement and sand.

Why use 1.27 as the dry factor?

It converts the wet mortar volume to the dry volume of cement and sand you buy. Some estimators use 1.3 and add 5% wastage, or add 20% for filling joints first. Pick one method and use it throughout; our 12 mm plaster post compares them.

Do I need to plaster the ceiling if I use a false ceiling?

Not under the false ceiling, but bathrooms, stairs and any slab soffit left exposed still need it. Take those areas out of the ceiling item only where the false ceiling is in the contract.

Is there a quick calculator?

Yes. The plaster calculator gives cement and sand for any area, thickness and mix, and the paint calculator uses the same wall area for the next stage. All tools are listed on the engineering tools page.

Sources and further reading

Preparing for the NEC licence or Lok Sewa exams? Estimation questions on plaster area and cement quantity come up often. Practise them on the engineering MCQ practice page.

Preparing for the NEC licence or Lok Sewa?Practise 2,100+ civil engineering MCQs with answers, free.Start practising

Comments

Need a calculator we don’t have yet?

Tell us what you use on site or in class. The most requested tools get built next.