Brick Wall Quantity for a House in Nepal: Bricks, Cement, Sand

Brick wall quantity for a house in Nepal: bricks, cement and sand per square metre of wall

To find the brick wall quantity for a house in Nepal, measure the net wall area (clear length between columns times the height below the beam, minus doors, windows and lintels), then multiply. With NBC 205 brick size 230 × 115 × 57 mm and 10 mm joints, one square metre of half-brick (115 mm) wall needs about 62 bricks, 0.16 bag of cement and 0.023 m³ of sand in 1:4 mortar. One square metre of one-brick (230 mm) wall needs about 124 bricks, 0.29 bag of cement and 0.060 m³ of sand in 1:6 mortar. Add about 5% to the bricks for breakage.

For the two-storey, 12-column house used in our beam and column examples, that works out to about 25,500 bricks, 58 bags of cement and 11 m³ (about 390 cft) of sand for all walls and the roof parapet. The rest of this guide shows where each number comes from, so you can redo it for your own drawing.

What NBC 205:2024 says about infill walls

Most new houses in Nepal are RC frames with brick infill. The walls carry their own weight and the weight of plaster, but they are not counted as structure. NBC 205:2024 (the ready-to-use code for low-rise RC buildings) sets the rules that decide your quantities:

  • Preferred brick size is 230 × 115 × 57 mm with 10 mm horizontal and vertical joints.
  • Bricks should have a crushing strength of at least 3.5 N/mm².
  • Walls are between half-brick and one-brick thick. Internal walls are half-brick; external walls can be up to one brick.
  • Mortar is cement-sand 1:6 for one-brick walls and 1:4 for half-brick walls. Adding lime at about a quarter to a half of the cement content is encouraged.
  • Staircase perimeter walls are 9 inches (one brick) thick.
  • No wall except a parapet should sit on a cantilever slab unless the cantilever is framed with beams.

So the usual Nepali house has two kinds of wall: 230 mm outer walls in 1:6 and 115 mm partition walls in 1:4. Keep them separate in your estimate, because the mortar mix and brick count per square metre are different.

Bricks, cement and sand per square metre of wall

Masons and contractors in Nepal think in wall area, not volume, and IS 1200 Part 3 (the measurement standard most Nepali estimates follow) also measures walls one brick thick or less in square metres. So work per m² of wall face.

Step 1: bricks per m² of wall face

Each brick on the wall face takes up its length plus one joint and its height plus one joint. For a 230 × 115 × 57 mm brick with 10 mm joints that is 0.240 × 0.067 = 0.01608 m², so:

  • Half-brick wall (one leaf): 1 ÷ 0.01608 = 62.19 bricks per m²
  • One-brick wall (two leaves): 2 × 62.19 = 124.38 bricks per m²

Step 2: wet mortar per m²

Wet mortar is the wall volume minus the volume of the bricks. One brick is 0.23 × 0.115 × 0.057 = 0.001508 m³.

  • Half-brick wall: 0.115 − 62.19 × 0.001508 = 0.0212 m³ per m²
  • One-brick wall (two leaves and a 10 mm middle joint, 0.240 m): 0.240 − 124.38 × 0.001508 = 0.0525 m³ per m²

Step 3: dry mortar, cement and sand

Dry cement and sand shrink when water is added, so multiply the wet volume by 1.33 (the same factor the site's brick calculator uses). Then split by the mix ratio and convert cement at 1440 kg/m³ and 50 kg per bag.

  • Half-brick in 1:4: dry 0.0212 × 1.33 = 0.0282 m³. Cement = 0.0282 ÷ 5 = 0.00565 m³ = 8.14 kg = 0.163 bag. Sand = 0.0282 × 4 ÷ 5 = 0.0226 m³.
  • One-brick in 1:6: dry 0.0525 × 1.33 = 0.0698 m³. Cement = 0.0698 ÷ 7 = 0.00997 m³ = 14.36 kg = 0.287 bag. Sand = 0.0698 × 6 ÷ 7 = 0.0598 m³.
BEAM 250 × 355 (with slab) PLINTH BEAM / FLOOR SLAB LINTEL 150 deep WINDOW 1.5 × 1.2 m deduct (over 0.1 m²) Clear length 3.65 m (4.0 m c/c − 0.35 m column) 2.645 m under beam How to measure 1. Clear length between columns 2. Height to the beam soffit 3. Minus openings and lintels 4. Net m² × rate 115 mm, 1:4 per m² 62.2 bricks 8.1 kg cement 0.023 m³ sand 230 mm, 1:6 per m² 124.4 bricks 14.4 kg cement 0.060 m³ sand
One wall panel between two columns. Measure the clear panel, deduct the window and lintel, then multiply the net area by the per m² rate for that wall type.

Per m² and per 100 sq ft table for common Nepali brick sizes

Kiln bricks in Nepal are not all the same size. Measure ten bricks from the stack you will buy, take the average, and use the matching row. The figures below are without wastage.

Brick size (mm)WallBricks per m²Cement per m²Sand per m²
230 × 115 × 57 (NBC 205)115 mm, 1:462.28.14 kg (0.163 bag)0.0226 m³
230 × 115 × 57 (NBC 205)230 mm, 1:6124.414.36 kg (0.287 bag)0.0598 m³
230 × 110 × 55 (common kiln)110 mm, 1:464.17.97 kg (0.159 bag)0.0221 m³
230 × 110 × 55 (common kiln)230 mm, 1:6128.214.12 kg (0.282 bag)0.0588 m³
240 × 115 × 57115 mm, 1:459.78.07 kg (0.161 bag)0.0224 m³
240 × 115 × 57240 mm, 1:6119.414.27 kg (0.285 bag)0.0595 m³

Per 100 sq ft (9.29 m²) of NBC-size wall: a half-brick wall needs about 578 bricks, 1.5 bags of cement and 7.4 cft of sand; a one-brick wall needs about 1,156 bricks, 2.7 bags of cement and 19.6 cft of sand.

Why not just use bricks per m³? Our post on how many bricks in 1 cubic metre gives about 498 bricks per m³ for this brick size. That figure assumes a mortar joint in all three directions. A half-brick wall has no joint across its thickness, so the m³ method gives 0.115 × 498 = 57 bricks per m², which is about 8% short of the 62 you will actually lay. For half-brick walls, always count by face area.

Step-by-step method for a whole house

  1. List the walls by type. Mark each wall on the plan as 230 mm or 115 mm. Parapet walls and staircase walls get their own lines.
  2. Take the clear length. In an RC frame, brickwork stops at the columns. Use the grid length minus the column width. If you want to use the centre-line idea for a load bearing house, see types of estimate and the centre line method.
  3. Take the height below the beam. Storey height minus beam depth (the beam depth includes the slab). With 3.0 m floor to floor and 355 mm beams, the wall is 2.645 m high.
  4. Deduct openings. Deduct every door, window and ventilator larger than 0.1 m². IS 1200 Part 3 does not deduct small openings or the ends of beams and lintels up to 0.1 m² in section. A 600 × 600 mm ventilator (0.36 m²) is deducted.
  5. Deduct concrete inside the wall. Lintels, sill bands and lintel bands are concrete items in the BOQ, so take them out of the brickwork. In the example below each lintel is 150 mm deep and bears 150 mm into the wall on each side.
  6. Multiply net area by the per m² rate for that wall type and mix.
  7. Add wastage to bricks only (5% for careful work; more for poor bricks or long carries). Do not add it a second time to mortar if you already used the 1.33 factor.

Worked example 1: one wall panel

An outer wall on a 4.0 m bay with 350 × 350 mm columns, one-brick thick in 1:6, with a 1.5 × 1.2 m window.

Clear length4.00 − 0.35 = 3.65 m
Height under beam3.00 − 0.355 = 2.645 m
Gross area3.65 × 2.645 = 9.654 m²
Window1.5 × 1.2 = 1.800 m²
Lintel face(1.5 + 0.3) × 0.15 = 0.270 m²
Net area9.654 − 1.800 − 0.270 = 7.584 m²
Bricks7.584 × 124.38 = 943, with 5% wastage about 991
Cement7.584 × 14.36 = 108.9 kg = 2.2 bags
Sand7.584 × 0.0598 = 0.454 m³ = 16.0 cft

Worked example 2: walls of a two-storey house

This is the same 12-column house used in the RCC beam quantity and RCC column quantity posts: a 3 × 4 column grid, X bays 3.5 + 4.0 m, Y bays 3.0 + 3.6 + 4.2 m, 350 mm columns, 3.0 m storeys and 355 mm deep beams. The opening sizes and the 16 m of internal partition per floor are example values; take yours from your drawing. Our guide to standard door and window sizes helps if the drawing has no schedule.

External walls (230 mm, 1:6), per floor

  • Grid perimeter = 2 × 7.5 + 2 × 10.8 = 36.6 m. Ten columns sit on the perimeter, so clear length = 36.6 − 10 × 0.35 = 33.1 m.
  • Gross area = 33.1 × 2.645 = 87.55 m².
  • Openings: 1 door 1.0 × 2.1 (2.10 m²), 5 windows 1.5 × 1.2 (9.00 m²), 2 ventilators 0.6 × 0.6 (0.72 m²) = 11.82 m².
  • Lintels: (1.3 + 5 × 1.8 + 2 × 0.9) × 0.15 = 1.815 m².
  • Net = 87.55 − 11.82 − 1.815 = 73.91 m².

Internal walls (115 mm, 1:4), per floor

  • Clear length 16.0 m, gross = 16.0 × 2.645 = 42.32 m².
  • Openings: 5 doors 0.9 × 2.1 (9.45 m²) and 2 bathroom doors 0.75 × 2.1 (3.15 m²) = 12.60 m².
  • Lintels: (5 × 1.2 + 2 × 1.05) × 0.15 = 1.215 m².
  • Net = 42.32 − 12.60 − 1.215 = 28.51 m².

Roof parapet (115 mm, 1:4)

The roof slab edge is 7.85 × 11.15 m (grid plus half a column on each side). A 115 mm parapet on the edge has a centre line of 2 × (7.85 + 11.15) − 4 × 0.115 = 37.54 m. At 1.0 m high (an example value; check your drawing and the municipality rules) the area is 37.54 m².

Total for two floors and the parapet

ItemNet areaBricksCementSand
230 mm walls, 1:6 (2 × 73.91)147.83 m²18,38742.5 bags8.84 m³
115 mm walls and parapet, 1:4 (2 × 28.51 + 37.54)94.55 m²5,88015.4 bags2.14 m³
Total242.38 m²24,267 (25,480 with 5%)57.8 bags10.98 m³ (388 cft)

Remember that plaster needs its own cement and sand on top of this; use the plaster quantity guide for both faces of every wall.

What it costs at a published municipal rate

Municipalities publish yearly rates for their own contracts. As an example, the Suryabinayak Municipality rate analysis 2081/82 lists chimney brick masonry (including materials, labour and 15% overhead) at Rs 15,517.07 per m³ in 1:6 and Rs 15,910.37 per m³ in 1:4 on the ground floor, and Rs 16,517.69 (1:6) and Rs 16,455.24 (1:4) on the first floor. Applying those rates to the volumes as drawn (230 and 115 mm):

ItemVolumeRate (Rs/m³)Amount (Rs)
230 mm walls, ground floor17.000 m³15,517.072,63,795
230 mm walls, first floor17.000 m³16,517.692,80,806
115 mm walls, ground floor3.278 m³15,910.3752,155
115 mm walls, first floor3.278 m³16,455.2453,942
Parapet4.317 m³16,455.2471,039
Total44.874 m³7,21,737

That is a rate for public works in one municipality for one fiscal year. Private contractor quotes, brick prices and labour vary by place and season, so check your own municipality's rate book or get two or three local quotes. For a full house budget, the house construction cost estimator puts walls next to the frame, finishes and services.

Common mistakes on Nepali sites

  • Using 500 bricks per m³ for every brick. That figure is for 190 × 90 × 90 mm modular bricks. Nepali kiln bricks are thinner, and the count per m² of half-brick wall is about 62 to 64, not 57.
  • Measuring walls through the columns. Taking the full grid length for an RC frame adds about 10% of brickwork that is really concrete (3.5 m of columns in 36.6 m of outer wall in the example).
  • Taking the wall up to the floor level above. The beam and slab take the top 355 mm or so. On a 3.0 m storey that alone is about 12% of the wall height.
  • Not deducting openings, or deducting tiny ones. Deduct doors, windows and ventilators; do not deduct holes for pipes or small openings up to 0.1 m².
  • One mix for all walls. NBC 205 asks for 1:4 in half-brick walls. Using 1:6 in partitions saves a few bags but makes thin walls weak.
  • Adding wastage twice. The 1.33 dry factor already covers the volume loss of mortar. Add 5% wastage to bricks, and only a small extra to cement if your site loses bags to rain or setting.
  • Forgetting parapets and staircase walls. In the example the parapet is about 40% of all half-brick area.
  • Buying all bricks at once without checking size. Measure ten bricks from each truck. A 5 mm change in brick length changes the count by about 2%, and a 5 mm change in height by about 7%.

Frequently asked questions

How many bricks for a 10 ft × 10 ft wall in Nepal?

100 sq ft is 9.29 m². For a half-brick wall that is about 578 NBC-size bricks (595 common 230 × 110 × 55 bricks) before wastage. For a 9 inch wall it is about 1,156 bricks. Deduct any door or window first.

How many cement bags for 1,000 bricks?

In a one-brick wall in 1:6, 1,000 bricks cover about 8.04 m², which needs about 2.3 bags. In a half-brick wall in 1:4, 1,000 bricks cover about 16.1 m² and need about 2.6 bags, because the mortar is richer.

Should the wall height be taken from the floor finish?

No. Brickwork starts on the plinth beam or slab and stops under the beam. Floor finish thickness does not change the brick count.

Can I use the brick calculator instead?

Yes. The brick calculator takes wall length, height, openings, brick size, joint and mix, and gives bricks, cement bags and sand. Enter the size you measured from your stack. It works one wall type at a time, so run it once for 230 mm walls and once for 115 mm walls.

Is this the same for a load bearing house?

The per m² rates are the same, but in a load bearing house walls are thicker, run through the corners and are measured by centre line in m³. Follow your drawing and NBC 202 for that case.

Women handling bricks at a building site in Kirtipur near Kathmandu, Nepal
Bricks being handled at a site in Kirtipur, near Kathmandu. Photo: Women Bricklayers - Kirtipur - Outside Kathmandu - Nepal by Adam Jones, CC BY-SA 2.0, via Wikimedia Commons

Sources and further reading

More free help: all engineering tools in one place, and estimation and building materials questions in the engineering MCQ practice section for Lok Sewa and NEC preparation.

Preparing for the NEC licence or Lok Sewa?Practise 2,100+ civil engineering MCQs with answers, free.Start practising