To find the brick wall quantity for a house in Nepal, measure the net wall area (clear length between columns times the height below the beam, minus doors, windows and lintels), then multiply. With NBC 205 brick size 230 × 115 × 57 mm and 10 mm joints, one square metre of half-brick (115 mm) wall needs about 62 bricks, 0.16 bag of cement and 0.023 m³ of sand in 1:4 mortar. One square metre of one-brick (230 mm) wall needs about 124 bricks, 0.29 bag of cement and 0.060 m³ of sand in 1:6 mortar. Add about 5% to the bricks for breakage.
For the two-storey, 12-column house used in our beam and column examples, that works out to about 25,500 bricks, 58 bags of cement and 11 m³ (about 390 cft) of sand for all walls and the roof parapet. The rest of this guide shows where each number comes from, so you can redo it for your own drawing.
What NBC 205:2024 says about infill walls
Most new houses in Nepal are RC frames with brick infill. The walls carry their own weight and the weight of plaster, but they are not counted as structure. NBC 205:2024 (the ready-to-use code for low-rise RC buildings) sets the rules that decide your quantities:
- Preferred brick size is 230 × 115 × 57 mm with 10 mm horizontal and vertical joints.
- Bricks should have a crushing strength of at least 3.5 N/mm².
- Walls are between half-brick and one-brick thick. Internal walls are half-brick; external walls can be up to one brick.
- Mortar is cement-sand 1:6 for one-brick walls and 1:4 for half-brick walls. Adding lime at about a quarter to a half of the cement content is encouraged.
- Staircase perimeter walls are 9 inches (one brick) thick.
- No wall except a parapet should sit on a cantilever slab unless the cantilever is framed with beams.
So the usual Nepali house has two kinds of wall: 230 mm outer walls in 1:6 and 115 mm partition walls in 1:4. Keep them separate in your estimate, because the mortar mix and brick count per square metre are different.
Bricks, cement and sand per square metre of wall
Masons and contractors in Nepal think in wall area, not volume, and IS 1200 Part 3 (the measurement standard most Nepali estimates follow) also measures walls one brick thick or less in square metres. So work per m² of wall face.
Step 1: bricks per m² of wall face
Each brick on the wall face takes up its length plus one joint and its height plus one joint. For a 230 × 115 × 57 mm brick with 10 mm joints that is 0.240 × 0.067 = 0.01608 m², so:
- Half-brick wall (one leaf): 1 ÷ 0.01608 = 62.19 bricks per m²
- One-brick wall (two leaves): 2 × 62.19 = 124.38 bricks per m²
Step 2: wet mortar per m²
Wet mortar is the wall volume minus the volume of the bricks. One brick is 0.23 × 0.115 × 0.057 = 0.001508 m³.
- Half-brick wall: 0.115 − 62.19 × 0.001508 = 0.0212 m³ per m²
- One-brick wall (two leaves and a 10 mm middle joint, 0.240 m): 0.240 − 124.38 × 0.001508 = 0.0525 m³ per m²
Step 3: dry mortar, cement and sand
Dry cement and sand shrink when water is added, so multiply the wet volume by 1.33 (the same factor the site's brick calculator uses). Then split by the mix ratio and convert cement at 1440 kg/m³ and 50 kg per bag.
- Half-brick in 1:4: dry 0.0212 × 1.33 = 0.0282 m³. Cement = 0.0282 ÷ 5 = 0.00565 m³ = 8.14 kg = 0.163 bag. Sand = 0.0282 × 4 ÷ 5 = 0.0226 m³.
- One-brick in 1:6: dry 0.0525 × 1.33 = 0.0698 m³. Cement = 0.0698 ÷ 7 = 0.00997 m³ = 14.36 kg = 0.287 bag. Sand = 0.0698 × 6 ÷ 7 = 0.0598 m³.
Per m² and per 100 sq ft table for common Nepali brick sizes
Kiln bricks in Nepal are not all the same size. Measure ten bricks from the stack you will buy, take the average, and use the matching row. The figures below are without wastage.
| Brick size (mm) | Wall | Bricks per m² | Cement per m² | Sand per m² |
|---|---|---|---|---|
| 230 × 115 × 57 (NBC 205) | 115 mm, 1:4 | 62.2 | 8.14 kg (0.163 bag) | 0.0226 m³ |
| 230 × 115 × 57 (NBC 205) | 230 mm, 1:6 | 124.4 | 14.36 kg (0.287 bag) | 0.0598 m³ |
| 230 × 110 × 55 (common kiln) | 110 mm, 1:4 | 64.1 | 7.97 kg (0.159 bag) | 0.0221 m³ |
| 230 × 110 × 55 (common kiln) | 230 mm, 1:6 | 128.2 | 14.12 kg (0.282 bag) | 0.0588 m³ |
| 240 × 115 × 57 | 115 mm, 1:4 | 59.7 | 8.07 kg (0.161 bag) | 0.0224 m³ |
| 240 × 115 × 57 | 240 mm, 1:6 | 119.4 | 14.27 kg (0.285 bag) | 0.0595 m³ |
Per 100 sq ft (9.29 m²) of NBC-size wall: a half-brick wall needs about 578 bricks, 1.5 bags of cement and 7.4 cft of sand; a one-brick wall needs about 1,156 bricks, 2.7 bags of cement and 19.6 cft of sand.
Why not just use bricks per m³? Our post on how many bricks in 1 cubic metre gives about 498 bricks per m³ for this brick size. That figure assumes a mortar joint in all three directions. A half-brick wall has no joint across its thickness, so the m³ method gives 0.115 × 498 = 57 bricks per m², which is about 8% short of the 62 you will actually lay. For half-brick walls, always count by face area.
Step-by-step method for a whole house
- List the walls by type. Mark each wall on the plan as 230 mm or 115 mm. Parapet walls and staircase walls get their own lines.
- Take the clear length. In an RC frame, brickwork stops at the columns. Use the grid length minus the column width. If you want to use the centre-line idea for a load bearing house, see types of estimate and the centre line method.
- Take the height below the beam. Storey height minus beam depth (the beam depth includes the slab). With 3.0 m floor to floor and 355 mm beams, the wall is 2.645 m high.
- Deduct openings. Deduct every door, window and ventilator larger than 0.1 m². IS 1200 Part 3 does not deduct small openings or the ends of beams and lintels up to 0.1 m² in section. A 600 × 600 mm ventilator (0.36 m²) is deducted.
- Deduct concrete inside the wall. Lintels, sill bands and lintel bands are concrete items in the BOQ, so take them out of the brickwork. In the example below each lintel is 150 mm deep and bears 150 mm into the wall on each side.
- Multiply net area by the per m² rate for that wall type and mix.
- Add wastage to bricks only (5% for careful work; more for poor bricks or long carries). Do not add it a second time to mortar if you already used the 1.33 factor.
Worked example 1: one wall panel
An outer wall on a 4.0 m bay with 350 × 350 mm columns, one-brick thick in 1:6, with a 1.5 × 1.2 m window.
| Clear length | 4.00 − 0.35 = 3.65 m |
| Height under beam | 3.00 − 0.355 = 2.645 m |
| Gross area | 3.65 × 2.645 = 9.654 m² |
| Window | 1.5 × 1.2 = 1.800 m² |
| Lintel face | (1.5 + 0.3) × 0.15 = 0.270 m² |
| Net area | 9.654 − 1.800 − 0.270 = 7.584 m² |
| Bricks | 7.584 × 124.38 = 943, with 5% wastage about 991 |
| Cement | 7.584 × 14.36 = 108.9 kg = 2.2 bags |
| Sand | 7.584 × 0.0598 = 0.454 m³ = 16.0 cft |
Worked example 2: walls of a two-storey house
This is the same 12-column house used in the RCC beam quantity and RCC column quantity posts: a 3 × 4 column grid, X bays 3.5 + 4.0 m, Y bays 3.0 + 3.6 + 4.2 m, 350 mm columns, 3.0 m storeys and 355 mm deep beams. The opening sizes and the 16 m of internal partition per floor are example values; take yours from your drawing. Our guide to standard door and window sizes helps if the drawing has no schedule.
External walls (230 mm, 1:6), per floor
- Grid perimeter = 2 × 7.5 + 2 × 10.8 = 36.6 m. Ten columns sit on the perimeter, so clear length = 36.6 − 10 × 0.35 = 33.1 m.
- Gross area = 33.1 × 2.645 = 87.55 m².
- Openings: 1 door 1.0 × 2.1 (2.10 m²), 5 windows 1.5 × 1.2 (9.00 m²), 2 ventilators 0.6 × 0.6 (0.72 m²) = 11.82 m².
- Lintels: (1.3 + 5 × 1.8 + 2 × 0.9) × 0.15 = 1.815 m².
- Net = 87.55 − 11.82 − 1.815 = 73.91 m².
Internal walls (115 mm, 1:4), per floor
- Clear length 16.0 m, gross = 16.0 × 2.645 = 42.32 m².
- Openings: 5 doors 0.9 × 2.1 (9.45 m²) and 2 bathroom doors 0.75 × 2.1 (3.15 m²) = 12.60 m².
- Lintels: (5 × 1.2 + 2 × 1.05) × 0.15 = 1.215 m².
- Net = 42.32 − 12.60 − 1.215 = 28.51 m².
Roof parapet (115 mm, 1:4)
The roof slab edge is 7.85 × 11.15 m (grid plus half a column on each side). A 115 mm parapet on the edge has a centre line of 2 × (7.85 + 11.15) − 4 × 0.115 = 37.54 m. At 1.0 m high (an example value; check your drawing and the municipality rules) the area is 37.54 m².
Total for two floors and the parapet
| Item | Net area | Bricks | Cement | Sand |
|---|---|---|---|---|
| 230 mm walls, 1:6 (2 × 73.91) | 147.83 m² | 18,387 | 42.5 bags | 8.84 m³ |
| 115 mm walls and parapet, 1:4 (2 × 28.51 + 37.54) | 94.55 m² | 5,880 | 15.4 bags | 2.14 m³ |
| Total | 242.38 m² | 24,267 (25,480 with 5%) | 57.8 bags | 10.98 m³ (388 cft) |
Remember that plaster needs its own cement and sand on top of this; use the plaster quantity guide for both faces of every wall.
What it costs at a published municipal rate
Municipalities publish yearly rates for their own contracts. As an example, the Suryabinayak Municipality rate analysis 2081/82 lists chimney brick masonry (including materials, labour and 15% overhead) at Rs 15,517.07 per m³ in 1:6 and Rs 15,910.37 per m³ in 1:4 on the ground floor, and Rs 16,517.69 (1:6) and Rs 16,455.24 (1:4) on the first floor. Applying those rates to the volumes as drawn (230 and 115 mm):
| Item | Volume | Rate (Rs/m³) | Amount (Rs) |
|---|---|---|---|
| 230 mm walls, ground floor | 17.000 m³ | 15,517.07 | 2,63,795 |
| 230 mm walls, first floor | 17.000 m³ | 16,517.69 | 2,80,806 |
| 115 mm walls, ground floor | 3.278 m³ | 15,910.37 | 52,155 |
| 115 mm walls, first floor | 3.278 m³ | 16,455.24 | 53,942 |
| Parapet | 4.317 m³ | 16,455.24 | 71,039 |
| Total | 44.874 m³ | 7,21,737 |
That is a rate for public works in one municipality for one fiscal year. Private contractor quotes, brick prices and labour vary by place and season, so check your own municipality's rate book or get two or three local quotes. For a full house budget, the house construction cost estimator puts walls next to the frame, finishes and services.
Common mistakes on Nepali sites
- Using 500 bricks per m³ for every brick. That figure is for 190 × 90 × 90 mm modular bricks. Nepali kiln bricks are thinner, and the count per m² of half-brick wall is about 62 to 64, not 57.
- Measuring walls through the columns. Taking the full grid length for an RC frame adds about 10% of brickwork that is really concrete (3.5 m of columns in 36.6 m of outer wall in the example).
- Taking the wall up to the floor level above. The beam and slab take the top 355 mm or so. On a 3.0 m storey that alone is about 12% of the wall height.
- Not deducting openings, or deducting tiny ones. Deduct doors, windows and ventilators; do not deduct holes for pipes or small openings up to 0.1 m².
- One mix for all walls. NBC 205 asks for 1:4 in half-brick walls. Using 1:6 in partitions saves a few bags but makes thin walls weak.
- Adding wastage twice. The 1.33 dry factor already covers the volume loss of mortar. Add 5% wastage to bricks, and only a small extra to cement if your site loses bags to rain or setting.
- Forgetting parapets and staircase walls. In the example the parapet is about 40% of all half-brick area.
- Buying all bricks at once without checking size. Measure ten bricks from each truck. A 5 mm change in brick length changes the count by about 2%, and a 5 mm change in height by about 7%.
Frequently asked questions
How many bricks for a 10 ft × 10 ft wall in Nepal?
100 sq ft is 9.29 m². For a half-brick wall that is about 578 NBC-size bricks (595 common 230 × 110 × 55 bricks) before wastage. For a 9 inch wall it is about 1,156 bricks. Deduct any door or window first.
How many cement bags for 1,000 bricks?
In a one-brick wall in 1:6, 1,000 bricks cover about 8.04 m², which needs about 2.3 bags. In a half-brick wall in 1:4, 1,000 bricks cover about 16.1 m² and need about 2.6 bags, because the mortar is richer.
Should the wall height be taken from the floor finish?
No. Brickwork starts on the plinth beam or slab and stops under the beam. Floor finish thickness does not change the brick count.
Can I use the brick calculator instead?
Yes. The brick calculator takes wall length, height, openings, brick size, joint and mix, and gives bricks, cement bags and sand. Enter the size you measured from your stack. It works one wall type at a time, so run it once for 230 mm walls and once for 115 mm walls.
Is this the same for a load bearing house?
The per m² rates are the same, but in a load bearing house walls are thicker, run through the corners and are measured by centre line in m³. Follow your drawing and NBC 202 for that case.
Sources and further reading
- NBC 205:2024, Ready-to-use detailing guideline for low-rise RC buildings (brick size, strength, wall thickness, mortar mixes).
- IS 1200 Part 3, Method of measurement of brickwork (walls of one brick or less in m², deductions).
- Suryabinayak Municipality rate analysis 2081/82 (brick masonry rates used above).