One 350 x 350 mm RCC column of a two storey house in Nepal, running from the top of the footing to the roof slab (about 6.95 m), needs about 0.85 m3 of M20 concrete, or roughly 7 bags of cement, and about 145 kg of Fe500 steel when it carries 4 bars of 16 mm plus 4 bars of 12 mm with 8 mm ties. That is about 170 kg of steel per cubic metre of column concrete. This page shows exactly how those numbers come out, so you can redo them for your own drawing, check a contractor's estimate, or answer the quantity questions that come up in the NEC licence and Lok Sewa exams.
The method below follows the column rules in NBC 205:2024, the Nepal National Building Code guideline for up to three storey RC framed residential buildings, and the general column rules in IS 456:2000. Always take the final bar sizes and spacing from your approved structural drawing; the values here are a worked example, not a design.
What NBC 205:2024 says about columns
Before counting anything, check that the column on your drawing matches the code. NBC 205:2024 (the 2024 ready to use detailing guideline that replaced the older rules of thumb) sets these points for columns of ordinary houses up to three storeys:
- Size: 350 x 350 mm or 400 x 400 mm. The old 230 x 230 mm column seen in many pre-2015 houses is not part of this guideline.
- Materials: M20 concrete and Fe500 (TMT) steel for all longitudinal bars and ties.
- Bars: taken from the tables for your seismic zone and soil type. For a two storey house the tables give 350 x 350 mm columns with 4-16 mm + 4-12 mm bars in many cases, and 8-16 mm or 4-20 mm + 4-16 mm for corner and staircase columns in the higher seismic zones.
- Ties: 8 mm at 75 mm in the end zones and 125 mm in the middle of the storey. The end zone length is the larger of H/6 and 450 mm.
- Hooks: 135 degree hooks with an extension of 6 times the bar diameter, but not less than 65 mm.
- Cover: 40 mm clear cover to the ties.
- Laps: not less than 57 times the bar diameter, only in the zone shown in the code figure, and not more than 50 percent of the bars lapped at one section.
- Storey height: a single storey is limited to 3.2 m.
IS 456:2000 adds the general limits that every column must meet: longitudinal steel at least 0.8 percent of the gross section and not more than 6 percent (4 percent in practice to avoid congestion), at least 4 bars in a rectangular column, bars not smaller than 12 mm, tie diameter at least one quarter of the largest bar and not less than 6 mm, and tie pitch not more than the least of the column width, 16 times the smallest longitudinal bar, or 300 mm.
Step-by-step method
- List the columns. Count columns by type from the structural plan: corner, face (edge), interior and staircase. They often carry different bars.
- Fix the height. Measure each column from the top of the footing to the underside of the roof slab. Let the slabs run through and deduct their thickness from the column at every floor, so the junction is not counted twice.
- Concrete volume. Width x depth x height. Multiply by 1.54 to get the dry volume and split it in the mix ratio (1 : 1.5 : 3 for nominal M20).
- Main bar length. Anchorage in the footing + full height + top anchorage + laps, minus bend allowances. Multiply by the number of bars.
- Ties. Work out one tie's cutting length, then the number of ties per storey using the close and normal spacing, then multiply.
- Weight. Length x D x D / 162 kg per metre for each diameter. Add 2 to 3 percent for cutting waste when you order.
- Check. Compare the steel per m3 of concrete with the usual range. A column at 50 kg per m3 or 400 kg per m3 means something has gone wrong.
Worked example 1: one column of a two storey house
Data for this example (typical values, replace with your own drawing):
| Item | Value |
|---|---|
| Column size | 350 x 350 mm |
| Top of footing below plinth level | 1.2 m |
| Floor to floor height | 3.0 m (two storeys) |
| Slab thickness | 125 mm |
| Footing thickness | 450 mm, 50 mm bottom cover |
| Main bars | 4-16 mm (corners) + 4-12 mm (mid faces), Fe500 |
| Ties | 8 mm, 75 mm in 500 mm end zones, 125 mm in the middle |
| Concrete | M20, nominal mix 1 : 1.5 : 3 |
Step 1: concrete
Height from top of footing to underside of roof slab = 1.2 + 3.0 + 3.0 - 0.125 - 0.125 = 6.95 m. The two slab thicknesses are taken out because the slabs are measured as full panels.
Volume = 0.35 x 0.35 x 6.95 = 0.851 m3.
Dry volume = 0.851 x 1.54 = 1.311 m3. The mix has 1 + 1.5 + 3 = 5.5 parts, so:
- Cement = 1.311 / 5.5 = 0.238 m3 x 1,440 kg per m3 = 343 kg = 6.9 bags of 50 kg
- Sand = 0.238 x 1.5 = 0.36 m3 (about 12.6 cft)
- Aggregate = 0.238 x 3 = 0.72 m3 (about 25.3 cft)
The same factors are explained in our post on cement bags for 1 m3 of M20 concrete, and you can check the volume with the concrete calculator.
Step 2: main bar length
Each bar starts at the bottom of the footing with an L bend, runs up through both storeys and ends with a bend into the roof slab. In this example:
- Vertical leg inside the footing = 450 - 50 = 400 mm
- L bend at the bottom = 300 mm (take the actual value from your drawing)
- Footing top to roof slab top = 1.2 + 3.0 + 3.0 = 7.2 m, less 40 mm top cover = 7.16 m
- Bend into the roof slab = 300 mm
Straight length = 0.40 + 0.30 + 7.16 + 0.30 = 8.16 m. One lap is needed at the first floor because the column is cast storey by storey. Lap = 57 x diameter, so 912 mm for 16 mm bars and 684 mm for 12 mm bars. Two 90 degree bends take off about 2 x 2d.
| Bar | Length per bar | Number | Total length | kg per m (D x D / 162) | Weight |
|---|---|---|---|---|---|
| 16 mm | 8.16 + 0.912 - 0.064 = 9.008 m | 4 | 36.03 m | 1.580 | 56.9 kg |
| 12 mm | 8.16 + 0.684 - 0.048 = 8.796 m | 4 | 35.18 m | 0.889 | 31.3 kg |
| Main bars total | 88.2 kg | ||||
Step 3: ties
Outer tie size = 350 - 2 x 40 = 270 mm. The centre line of an 8 mm tie is 270 - 8 = 262 mm. With two 135 degree hooks of 80 mm each (10d, above the 65 mm minimum) and deductions of 2d for each of three 90 degree corners and 3d for each 135 degree bend:
Closed tie = 4 x 262 + 2 x 80 - 3 x 16 - 2 x 24 = 1,112 mm.
For the 8-bar arrangement this example adds two straight cross ties at each level to hold the middle bars: 262 + 2 x 80 - 2 x 24 = 374 mm each. If your drawing shows an inner diamond tie instead, work out its length the same way.
Number of tie levels:
- Each 3.0 m storey: two 500 mm end zones at 75 mm = 2 x 7 = 14, middle 2,000 mm at 125 mm = 16, plus 1 = 31
- 1.2 m below plinth: 500 mm at 75 mm = 7, remaining 700 mm at 125 mm = 6, total 13
- Two ties inside the footing to hold the cage = 2
- Total = 31 + 31 + 13 + 2 = 77 tie levels
Tie steel = 77 x 1.112 = 85.6 m of closed ties plus 77 x 2 x 0.374 = 57.6 m of cross ties = 143.2 m of 8 mm bar. At 0.395 kg per m that is 56.6 kg.
Step 4: total and check
Steel for one column = 88.2 + 56.6 = 144.8 kg, or about 149 kg with 3 percent wastage. Steel per m3 = 144.8 / 0.851 = 170 kg per m3. Steel ratio of the main bars = (4 x 201.1 + 4 x 113.1) / (350 x 350) = 1,256.6 / 122,500 = 1.03 percent, which is above the 0.8 percent minimum of IS 456. The 125 mm tie spacing is also inside the IS 456 limit of 192 mm (16 x 12 mm).
Notice that the ties are almost 40 percent of the column steel. Estimates that only count the long bars are always short.
Worked example 2: all columns of a 12-column house
A common two storey house in the Terai or the Kathmandu valley has a 3 x 4 grid, so 12 columns. If all 12 are the same as Example 1:
| Item | One column | 12 columns |
|---|---|---|
| Concrete | 0.851 m3 | 10.2 m3 |
| Cement (50 kg bags) | 6.9 | 82.4 |
| Sand | 0.36 m3 | 4.3 m3 |
| Aggregate | 0.72 m3 | 8.6 m3 |
| Steel (net) | 144.8 kg | 1,737.5 kg |
| Steel with 3 percent wastage | 149.1 kg | 1,789.6 kg (about 1.8 t) |
In practice the four corner columns and the staircase columns may carry 8-16 mm or 4-20 + 4-16 mm in higher seismic zones, so run a separate line for each column type. The staircase columns are often taller too, because they go up to the stair cover (mumty) roof.
Quick reference tables
Concrete and cement per metre height of column
| Column size | Concrete per m (m3) | Cement bags per m (M20 nominal) | Note |
|---|---|---|---|
| 230 x 230 mm | 0.053 | 0.43 | Old practice, not in NBC 205:2024 |
| 300 x 300 mm | 0.090 | 0.73 | For comparison |
| 350 x 350 mm | 0.123 | 0.99 | NBC 205:2024 size |
| 400 x 400 mm | 0.160 | 1.29 | NBC 205:2024 size |
Main bar weight per metre and steel ratio
| Bars | Area (mm2) | kg per m of column | Percent in 350 x 350 | Percent in 400 x 400 |
|---|---|---|---|---|
| 4-12 mm | 452 | 3.56 | 0.37 (below 0.8, not allowed) | 0.28 (not allowed) |
| 4-16 + 4-12 mm | 1,257 | 9.88 | 1.03 | 0.79 (just below 0.8) |
| 8-16 mm | 1,608 | 12.64 | 1.31 | 1.01 |
| 4-20 + 4-16 mm | 2,061 | 16.20 | 1.68 | 1.29 |
The second row is a useful warning: the same 4-16 + 4-12 mm bars that are fine in a 350 mm column fall just under the 0.8 percent minimum in a 400 mm column. A bigger column does not always mean the same bars can be reused. Find any bar weight quickly with the steel weight calculator or our note on the D x D / 162 formula.
Common mistakes seen on Nepali sites
- Counting the column through the slab and the slab over the column. The joint gets paid twice. Pick one rule and apply it to the whole estimate.
- Forgetting the part below plinth. The column from the top of the footing to the plinth beam is often 1 to 1.5 m and is easy to miss when you read heights from the floor plans.
- Ties at one spacing. Contractors sometimes place ties at 150 mm all the way up. NBC 205:2024 asks for 75 mm in the end zones, because the ends of a column take the highest bending and shear in an earthquake.
- 90 degree hooks on ties. Ties need 135 degree hooks bent back into the core. A 90 degree hook opens up when the cover spalls.
- All bars lapped at the same level. The code allows only half the bars to be lapped at one section, and only in the middle part of the storey, not just above the floor where it is most convenient.
- Short laps. At 57 times the diameter a 16 mm bar needs a 912 mm lap. Starter bars left 600 mm above the slab are too short.
- No wastage or wrong stock length. Bars come in 12 m lengths. A 9 m bar leaves a 3 m off-cut, so plan cutting before you order.
Frequently asked questions
How many kg of steel are in one column of a house?
For a 350 x 350 mm column of a two storey house with 4-16 + 4-12 mm bars and 8 mm ties, about 145 kg from footing to roof, or about 21 kg per metre of height including ties. Corner columns with 8-16 mm bars carry about 30 percent more main bar steel.
What is the minimum column size for a house in Nepal?
NBC 205:2024 gives 350 x 350 mm or 400 x 400 mm columns for RC framed houses up to three storeys. Municipalities check the structural drawings during naksa pass, so follow the approved drawing. See our guide to the naksa pass process.
How many cement bags for one column?
About 1 bag per metre of height for a 350 x 350 mm column in nominal M20 mix, so about 7 bags for a column of about 7 m.
Why do we deduct slab thickness from the column height?
Because the slab is measured as a full panel over the columns. If you do not deduct it, the concrete at each joint is counted twice.
Is 170 kg of steel per m3 normal for columns?
It is what this example gives for a 350 mm column with 8 bars and close tie spacing. With 8-16 mm bars the same column comes to about 200 kg per m3. Use these figures only to check your own calculation, not as design values.
Related tools and practice
This post is part of a series on house quantities. Read the isolated footing quantity and RCC slab quantity examples, the bar bending schedule for beams, and test yourself on the engineering MCQ practice page before the licence exam.
Sources
- NBC 205:2024 detailing guideline for RC buildings up to three storeys (PDF hosted by Birendranagar Municipality)
- IS 456:2000 Plain and Reinforced Concrete, clauses 26.4 and 26.5.3
- Department of Urban Development and Building Construction (DUDBC)
Rules for seismic zone, soil type and column bars differ between sites. Confirm the final details with your designer and your municipality's building section.