RCC Column Concrete and Steel Quantity: Worked Example for Nepal

RCC column concrete and steel quantity worked example for a 350 x 350 mm column in Nepal

One 350 x 350 mm RCC column of a two storey house in Nepal, running from the top of the footing to the roof slab (about 6.95 m), needs about 0.85 m3 of M20 concrete, or roughly 7 bags of cement, and about 145 kg of Fe500 steel when it carries 4 bars of 16 mm plus 4 bars of 12 mm with 8 mm ties. That is about 170 kg of steel per cubic metre of column concrete. This page shows exactly how those numbers come out, so you can redo them for your own drawing, check a contractor's estimate, or answer the quantity questions that come up in the NEC licence and Lok Sewa exams.

The method below follows the column rules in NBC 205:2024, the Nepal National Building Code guideline for up to three storey RC framed residential buildings, and the general column rules in IS 456:2000. Always take the final bar sizes and spacing from your approved structural drawing; the values here are a worked example, not a design.

What NBC 205:2024 says about columns

Before counting anything, check that the column on your drawing matches the code. NBC 205:2024 (the 2024 ready to use detailing guideline that replaced the older rules of thumb) sets these points for columns of ordinary houses up to three storeys:

  • Size: 350 x 350 mm or 400 x 400 mm. The old 230 x 230 mm column seen in many pre-2015 houses is not part of this guideline.
  • Materials: M20 concrete and Fe500 (TMT) steel for all longitudinal bars and ties.
  • Bars: taken from the tables for your seismic zone and soil type. For a two storey house the tables give 350 x 350 mm columns with 4-16 mm + 4-12 mm bars in many cases, and 8-16 mm or 4-20 mm + 4-16 mm for corner and staircase columns in the higher seismic zones.
  • Ties: 8 mm at 75 mm in the end zones and 125 mm in the middle of the storey. The end zone length is the larger of H/6 and 450 mm.
  • Hooks: 135 degree hooks with an extension of 6 times the bar diameter, but not less than 65 mm.
  • Cover: 40 mm clear cover to the ties.
  • Laps: not less than 57 times the bar diameter, only in the zone shown in the code figure, and not more than 50 percent of the bars lapped at one section.
  • Storey height: a single storey is limited to 3.2 m.

IS 456:2000 adds the general limits that every column must meet: longitudinal steel at least 0.8 percent of the gross section and not more than 6 percent (4 percent in practice to avoid congestion), at least 4 bars in a rectangular column, bars not smaller than 12 mm, tie diameter at least one quarter of the largest bar and not less than 6 mm, and tie pitch not more than the least of the column width, 16 times the smallest longitudinal bar, or 300 mm.

Step-by-step method

  1. List the columns. Count columns by type from the structural plan: corner, face (edge), interior and staircase. They often carry different bars.
  2. Fix the height. Measure each column from the top of the footing to the underside of the roof slab. Let the slabs run through and deduct their thickness from the column at every floor, so the junction is not counted twice.
  3. Concrete volume. Width x depth x height. Multiply by 1.54 to get the dry volume and split it in the mix ratio (1 : 1.5 : 3 for nominal M20).
  4. Main bar length. Anchorage in the footing + full height + top anchorage + laps, minus bend allowances. Multiply by the number of bars.
  5. Ties. Work out one tie's cutting length, then the number of ties per storey using the close and normal spacing, then multiply.
  6. Weight. Length x D x D / 162 kg per metre for each diameter. Add 2 to 3 percent for cutting waste when you order.
  7. Check. Compare the steel per m3 of concrete with the usual range. A column at 50 kg per m3 or 400 kg per m3 means something has gone wrong.
One storey of a 350 x 350 mm column (NBC 205:2024 style) slab / beam above floor below end zone ties @ 75 end zone ties @ 75 middle ties @ 125 lap zone (middle half, 57 x dia) End zone = larger of H/6 and 450 mm. Example: H = 3.0 m, so 500 mm at each end. Section A-A 350 x 350 mm, M20, Fe500 4 x 16 mm at corners 4 x 12 mm at mid faces 8 mm tie + 2 cross ties 40 mm clear cover to ties
How the ties are spaced along one storey of a column, and the 8-bar section used in the worked example. Draw your own count from the structural drawing; the cross tie detail varies between designs.

Worked example 1: one column of a two storey house

Data for this example (typical values, replace with your own drawing):

ItemValue
Column size350 x 350 mm
Top of footing below plinth level1.2 m
Floor to floor height3.0 m (two storeys)
Slab thickness125 mm
Footing thickness450 mm, 50 mm bottom cover
Main bars4-16 mm (corners) + 4-12 mm (mid faces), Fe500
Ties8 mm, 75 mm in 500 mm end zones, 125 mm in the middle
ConcreteM20, nominal mix 1 : 1.5 : 3

Step 1: concrete

Height from top of footing to underside of roof slab = 1.2 + 3.0 + 3.0 - 0.125 - 0.125 = 6.95 m. The two slab thicknesses are taken out because the slabs are measured as full panels.

Volume = 0.35 x 0.35 x 6.95 = 0.851 m3.

Dry volume = 0.851 x 1.54 = 1.311 m3. The mix has 1 + 1.5 + 3 = 5.5 parts, so:

  • Cement = 1.311 / 5.5 = 0.238 m3 x 1,440 kg per m3 = 343 kg = 6.9 bags of 50 kg
  • Sand = 0.238 x 1.5 = 0.36 m3 (about 12.6 cft)
  • Aggregate = 0.238 x 3 = 0.72 m3 (about 25.3 cft)

The same factors are explained in our post on cement bags for 1 m3 of M20 concrete, and you can check the volume with the concrete calculator.

Step 2: main bar length

Each bar starts at the bottom of the footing with an L bend, runs up through both storeys and ends with a bend into the roof slab. In this example:

  • Vertical leg inside the footing = 450 - 50 = 400 mm
  • L bend at the bottom = 300 mm (take the actual value from your drawing)
  • Footing top to roof slab top = 1.2 + 3.0 + 3.0 = 7.2 m, less 40 mm top cover = 7.16 m
  • Bend into the roof slab = 300 mm

Straight length = 0.40 + 0.30 + 7.16 + 0.30 = 8.16 m. One lap is needed at the first floor because the column is cast storey by storey. Lap = 57 x diameter, so 912 mm for 16 mm bars and 684 mm for 12 mm bars. Two 90 degree bends take off about 2 x 2d.

BarLength per barNumberTotal lengthkg per m (D x D / 162)Weight
16 mm8.16 + 0.912 - 0.064 = 9.008 m436.03 m1.58056.9 kg
12 mm8.16 + 0.684 - 0.048 = 8.796 m435.18 m0.88931.3 kg
Main bars total88.2 kg

Step 3: ties

Outer tie size = 350 - 2 x 40 = 270 mm. The centre line of an 8 mm tie is 270 - 8 = 262 mm. With two 135 degree hooks of 80 mm each (10d, above the 65 mm minimum) and deductions of 2d for each of three 90 degree corners and 3d for each 135 degree bend:

Closed tie = 4 x 262 + 2 x 80 - 3 x 16 - 2 x 24 = 1,112 mm.

For the 8-bar arrangement this example adds two straight cross ties at each level to hold the middle bars: 262 + 2 x 80 - 2 x 24 = 374 mm each. If your drawing shows an inner diamond tie instead, work out its length the same way.

Number of tie levels:

  • Each 3.0 m storey: two 500 mm end zones at 75 mm = 2 x 7 = 14, middle 2,000 mm at 125 mm = 16, plus 1 = 31
  • 1.2 m below plinth: 500 mm at 75 mm = 7, remaining 700 mm at 125 mm = 6, total 13
  • Two ties inside the footing to hold the cage = 2
  • Total = 31 + 31 + 13 + 2 = 77 tie levels

Tie steel = 77 x 1.112 = 85.6 m of closed ties plus 77 x 2 x 0.374 = 57.6 m of cross ties = 143.2 m of 8 mm bar. At 0.395 kg per m that is 56.6 kg.

Step 4: total and check

Steel for one column = 88.2 + 56.6 = 144.8 kg, or about 149 kg with 3 percent wastage. Steel per m3 = 144.8 / 0.851 = 170 kg per m3. Steel ratio of the main bars = (4 x 201.1 + 4 x 113.1) / (350 x 350) = 1,256.6 / 122,500 = 1.03 percent, which is above the 0.8 percent minimum of IS 456. The 125 mm tie spacing is also inside the IS 456 limit of 192 mm (16 x 12 mm).

Notice that the ties are almost 40 percent of the column steel. Estimates that only count the long bars are always short.

RCC framed house under construction near Kathmandu with exposed columns and workers on the top floor
A typical RCC framed house under construction in the Kathmandu valley: the columns are cast storey by storey, which is why every column needs laps at each floor. Photo: Building a house nearby the street between Kathmandu and Nagarkot by Rainer Haessner, CC BY-SA 3.0, via Wikimedia Commons (cropped).

Worked example 2: all columns of a 12-column house

A common two storey house in the Terai or the Kathmandu valley has a 3 x 4 grid, so 12 columns. If all 12 are the same as Example 1:

ItemOne column12 columns
Concrete0.851 m310.2 m3
Cement (50 kg bags)6.982.4
Sand0.36 m34.3 m3
Aggregate0.72 m38.6 m3
Steel (net)144.8 kg1,737.5 kg
Steel with 3 percent wastage149.1 kg1,789.6 kg (about 1.8 t)

In practice the four corner columns and the staircase columns may carry 8-16 mm or 4-20 + 4-16 mm in higher seismic zones, so run a separate line for each column type. The staircase columns are often taller too, because they go up to the stair cover (mumty) roof.

Quick reference tables

Concrete and cement per metre height of column

Column sizeConcrete per m (m3)Cement bags per m (M20 nominal)Note
230 x 230 mm0.0530.43Old practice, not in NBC 205:2024
300 x 300 mm0.0900.73For comparison
350 x 350 mm0.1230.99NBC 205:2024 size
400 x 400 mm0.1601.29NBC 205:2024 size

Main bar weight per metre and steel ratio

BarsArea (mm2)kg per m of columnPercent in 350 x 350Percent in 400 x 400
4-12 mm4523.560.37 (below 0.8, not allowed)0.28 (not allowed)
4-16 + 4-12 mm1,2579.881.030.79 (just below 0.8)
8-16 mm1,60812.641.311.01
4-20 + 4-16 mm2,06116.201.681.29

The second row is a useful warning: the same 4-16 + 4-12 mm bars that are fine in a 350 mm column fall just under the 0.8 percent minimum in a 400 mm column. A bigger column does not always mean the same bars can be reused. Find any bar weight quickly with the steel weight calculator or our note on the D x D / 162 formula.

Common mistakes seen on Nepali sites

  • Counting the column through the slab and the slab over the column. The joint gets paid twice. Pick one rule and apply it to the whole estimate.
  • Forgetting the part below plinth. The column from the top of the footing to the plinth beam is often 1 to 1.5 m and is easy to miss when you read heights from the floor plans.
  • Ties at one spacing. Contractors sometimes place ties at 150 mm all the way up. NBC 205:2024 asks for 75 mm in the end zones, because the ends of a column take the highest bending and shear in an earthquake.
  • 90 degree hooks on ties. Ties need 135 degree hooks bent back into the core. A 90 degree hook opens up when the cover spalls.
  • All bars lapped at the same level. The code allows only half the bars to be lapped at one section, and only in the middle part of the storey, not just above the floor where it is most convenient.
  • Short laps. At 57 times the diameter a 16 mm bar needs a 912 mm lap. Starter bars left 600 mm above the slab are too short.
  • No wastage or wrong stock length. Bars come in 12 m lengths. A 9 m bar leaves a 3 m off-cut, so plan cutting before you order.

Frequently asked questions

How many kg of steel are in one column of a house?

For a 350 x 350 mm column of a two storey house with 4-16 + 4-12 mm bars and 8 mm ties, about 145 kg from footing to roof, or about 21 kg per metre of height including ties. Corner columns with 8-16 mm bars carry about 30 percent more main bar steel.

What is the minimum column size for a house in Nepal?

NBC 205:2024 gives 350 x 350 mm or 400 x 400 mm columns for RC framed houses up to three storeys. Municipalities check the structural drawings during naksa pass, so follow the approved drawing. See our guide to the naksa pass process.

How many cement bags for one column?

About 1 bag per metre of height for a 350 x 350 mm column in nominal M20 mix, so about 7 bags for a column of about 7 m.

Why do we deduct slab thickness from the column height?

Because the slab is measured as a full panel over the columns. If you do not deduct it, the concrete at each joint is counted twice.

Is 170 kg of steel per m3 normal for columns?

It is what this example gives for a 350 mm column with 8 bars and close tie spacing. With 8-16 mm bars the same column comes to about 200 kg per m3. Use these figures only to check your own calculation, not as design values.

Related tools and practice

This post is part of a series on house quantities. Read the isolated footing quantity and RCC slab quantity examples, the bar bending schedule for beams, and test yourself on the engineering MCQ practice page before the licence exam.

Sources

Rules for seismic zone, soil type and column bars differ between sites. Confirm the final details with your designer and your municipality's building section.

Preparing for the NEC licence or Lok Sewa?Practise 2,100+ civil engineering MCQs with answers, free.Start practising

Comments

Need a calculator we don’t have yet?

Tell us what you use on site or in class. The most requested tools get built next.