One cubic metre of M20 concrete with a nominal mix of 1:1.5:3 needs about 8 bags of cement (403 kg). It also needs about 0.42 m³ (14.8 cft) of sand and 0.84 m³ (29.7 cft) of coarse aggregate (gitti).
These are standard textbook quantities for nominal mix concrete. The working below uses a dry volume factor of 1.54 and a cement density of 1440 kg/m³.
Cement bags for 1 m³ of M20 concrete: step by step
- Wet volume = 1 m³.
- Dry volume = 1 × 1.54 = 1.54 m³. Dry materials lose volume once water is added and the fine particles fill the gaps between stones, so you need about 54% more dry material than the finished concrete.
- Sum of ratio = 1 + 1.5 + 3 = 5.5.
- Cement = 1.54 × 1 ÷ 5.5 = 0.28 m³. Weight = 0.28 × 1440 = 403.2 kg. Bags = 403.2 ÷ 50 = 8.06, say 8 bags.
- Sand = 1.54 × 1.5 ÷ 5.5 = 0.42 m³ = 0.42 × 35.3147 = 14.83 cft.
- Aggregate = 1.54 × 3 ÷ 5.5 = 0.84 m³ = 29.66 cft.
One 50 kg bag of cement has a volume of 50 ÷ 1440 = 0.0347 m³ (about 1.23 cft). That is why 0.28 m³ of cement works out to roughly 8 bags.
Table for M15, M20 and M25 per m³
| Grade (nominal mix) | Cement (kg) | Cement (bags) | Sand (m³ / cft) | Aggregate (m³ / cft) |
|---|---|---|---|---|
| M15 (1:2:4) | 316.8 | 6.34 | 0.44 / 15.54 | 0.88 / 31.08 |
| M20 (1:1.5:3) | 403.2 | 8.06 | 0.42 / 14.83 | 0.84 / 29.66 |
| M25 (1:1:2) | 554.4 | 11.09 | 0.385 / 13.60 | 0.77 / 27.19 |
IS 456 lists nominal mixes only up to M20. For M25 and above, a design mix from lab trials is the proper method, and it often uses less cement than the 1:1:2 rule of thumb. Treat the M25 row as a rough site check only. These figures do not include wastage; many estimators add 2 to 5%.
Worked example
A slab needs 4.5 m³ of M20 concrete. Cement = 4.5 × 8.064 = 36.3, so order 37 bags. Sand = 4.5 × 14.83 = 66.7 cft. Aggregate = 4.5 × 29.66 = 133.5 cft.
Use the concrete calculator for other volumes and mixes, and the unit converter to switch between m³ and cft.
Mixing M20 on site, one bag at a time
Many house sites in Nepal mix concrete one bag of cement per batch in a drum mixer. One 50 kg bag is 50 / 1,440 = 0.0347 m3, about 1.23 cft. For a 1:1.5:3 mix, each bag needs:
- Sand: 1.5 x 1.23 = 1.84 cft.
- Aggregate: 3 x 1.23 = 3.68 cft.
- Water: 22.5 to 25 litres at a water-cement ratio of 0.45 to 0.50, less if the sand is wet.
The easy way to get these volumes right is a measuring box (farma) with the same volume as one bag. A box 350 x 250 x 400 mm inside holds 0.035 m3. Fill it level: 1.5 boxes of sand and 3 boxes of aggregate per bag. Headpans (tasla) and wheelbarrows are not a fixed volume, so a mix counted in "8 tasla of gitti" can drift far from 1:1.5:3.
Worked example 2: M20 for a whole 2-storey house
These are the M20 volumes from our cement and steel summary for a 12-column, 2-storey house, worked with the same 1.54 factor as above (no wastage):
| Element | M20 (m3) | Cement (bags) | Sand (cft) | Aggregate (cft) |
|---|---|---|---|---|
| Footings | 8.41 | 67.8 | 124.7 | 249.5 |
| Columns | 10.22 | 82.4 | 151.6 | 303.2 |
| Beams (plinth and floors) | 11.51 | 92.8 | 170.7 | 341.4 |
| Slabs | 21.04 | 169.7 | 312.1 | 624.1 |
| Stair | 1.45 | 11.7 | 21.5 | 43.0 |
| Total | 52.63 | 424.4 | 780.6 | 1,561.2 |
With 3% wastage that is about 437 bags. The slabs take 40% of the cement, so the slab pour is where a short delivery hurts most. Order the cement for a whole slab before the pour starts; a stop halfway leaves a cold joint.
What it costs
The Suryabinayak Municipality rate analysis for 2081/82 gives Rs 17,320.55 per m3 for machine-mixed 1:1.5:3 concrete and Rs 17,591.83 per m3 for M20 ready-mixed concrete, both including 15% overhead. For the 4.5 m3 slab in the first example that is about Rs 77,942 site-mixed or Rs 79,163 ready-mixed. The two are close at these rates, so for a large slab with a narrow access lane, ready-mix often makes sense for speed and quality. Rates change by municipality and year; ask your municipality for the current list.
Common mistakes on site
- Adding extra water to make the mix flow. More water lowers strength more than any small error in sand or aggregate. Keep to the ratio and use a vibrator.
- Counting sand in wheelbarrows or headpans of unknown size instead of a measuring box.
- Using the 8 bags rule for M25. M25 by the 1:1:2 rule takes about 11 bags per m3, and IS 456 expects a design mix above M20.
- Forgetting wastage. Allow 2 to 5% for spillage and bags that set hard in storage.
- Storing bags on bare ground. Stack them on planks off the floor and away from walls, and use older bags first.
- Skipping cube tests. The bag count only tells you what went into the mixer, not the strength. A set of cubes from each pour, tested at 7 and 28 days, tells you that.
Frequently asked questions
Why 1.54 and not 1.52 or 1.57?
Different books use values from about 1.52 to 1.57. The difference is small, around 2% in cement. 1.54 is widely used in Nepali and Indian estimating practice.
How much water does 1 m³ of M20 need?
At a water-cement ratio of 0.45 to 0.50, it is about 181 to 202 litres for 403 kg of cement. Adjust on site for wet sand.
Does M20 always mean 1:1.5:3?
No. M20 means a characteristic strength of 20 N/mm² at 28 days. The 1:1.5:3 nominal mix is one way to aim for it. Cube tests confirm whether you got it.