How Many Cement Bags in 1 m³ of M20 Concrete (1:1.5:3)

One cubic metre of M20 concrete with a nominal mix of 1:1.5:3 needs about 8 bags of cement (403 kg). It also needs about 0.42 m³ (14.8 cft) of sand and 0.84 m³ (29.7 cft) of coarse aggregate (gitti).

These are standard textbook quantities for nominal mix concrete. The working below uses a dry volume factor of 1.54 and a cement density of 1440 kg/m³.

Cement bags for 1 m³ of M20 concrete: step by step

  1. Wet volume = 1 m³.
  2. Dry volume = 1 × 1.54 = 1.54 m³. Dry materials lose volume once water is added and the fine particles fill the gaps between stones, so you need about 54% more dry material than the finished concrete.
  3. Sum of ratio = 1 + 1.5 + 3 = 5.5.
  4. Cement = 1.54 × 1 ÷ 5.5 = 0.28 m³. Weight = 0.28 × 1440 = 403.2 kg. Bags = 403.2 ÷ 50 = 8.06, say 8 bags.
  5. Sand = 1.54 × 1.5 ÷ 5.5 = 0.42 m³ = 0.42 × 35.3147 = 14.83 cft.
  6. Aggregate = 1.54 × 3 ÷ 5.5 = 0.84 m³ = 29.66 cft.

One 50 kg bag of cement has a volume of 50 ÷ 1440 = 0.0347 m³ (about 1.23 cft). That is why 0.28 m³ of cement works out to roughly 8 bags.

Wet concrete: 1 m³ 1.00 m³ Dry materials: 1.54 m³ (M20, 1:1.5:3) 0.28 0.42 0.84 Cement Sand Aggregate 8.06 bags 14.83 cft 29.66 cft = 1.54 m³
Bars drawn to the same scale: 1 m³ of wet M20 concrete comes from 1.54 m³ of dry materials.

Table for M15, M20 and M25 per m³

Grade (nominal mix)Cement (kg)Cement (bags)Sand (m³ / cft)Aggregate (m³ / cft)
M15 (1:2:4)316.86.340.44 / 15.540.88 / 31.08
M20 (1:1.5:3)403.28.060.42 / 14.830.84 / 29.66
M25 (1:1:2)554.411.090.385 / 13.600.77 / 27.19

IS 456 lists nominal mixes only up to M20. For M25 and above, a design mix from lab trials is the proper method, and it often uses less cement than the 1:1:2 rule of thumb. Treat the M25 row as a rough site check only. These figures do not include wastage; many estimators add 2 to 5%.

Worked example

A slab needs 4.5 m³ of M20 concrete. Cement = 4.5 × 8.064 = 36.3, so order 37 bags. Sand = 4.5 × 14.83 = 66.7 cft. Aggregate = 4.5 × 29.66 = 133.5 cft.

Use the concrete calculator for other volumes and mixes, and the unit converter to switch between m³ and cft.

Frequently asked questions

Why 1.54 and not 1.52 or 1.57?

Different books use values from about 1.52 to 1.57. The difference is small, around 2% in cement. 1.54 is widely used in Nepali and Indian estimating practice.

How much water does 1 m³ of M20 need?

At a water-cement ratio of 0.45 to 0.50, it is about 181 to 202 litres for 403 kg of cement. Adjust on site for wet sand.

Does M20 always mean 1:1.5:3?

No. M20 means a characteristic strength of 20 N/mm² at 28 days. The 1:1.5:3 nominal mix is one way to aim for it. Cube tests confirm whether you got it.