A two storey RCC framed house in Nepal with about 175 m2 (1,884 sq ft) of built-up area needs roughly 640 bags of cement, 5.9 tonnes of steel, 53 m3 (about 1,880 cft) of sand, 52 m3 (about 1,835 cft) of aggregate and 25,500 bricks for the frame, walls, plaster and floor bedding. That works out to about 0.34 bag of cement and 3.1 kg of steel per square foot. These totals come from adding up, element by element, the worked examples in our estimating series for one 12-column house, so every number below can be traced back and checked.
Owners use a summary like this to plan purchases by stage and to test a contractor's material claims. Students meet the same exercise as the abstract of quantities in estimating and costing. The ratios at the end are only a first check; your own drawings decide the real figures.
The example house
All the element posts in this series use the same building, so the quantities fit together without double counting.
| Item | Value used |
|---|---|
| Frame | RCC, 3 x 4 grid, 12 columns 350 x 350 mm |
| Bays | X: 3.5 + 4.0 m, Y: 3.0 + 3.6 + 4.2 m (centre to centre) |
| Slab edge | 7.85 x 11.15 m = 87.53 m2 per floor |
| Storeys | Ground + first, 3.0 m floor to floor, flat roof slab |
| Built-up area | 2 x 87.53 = 175.06 m2 = 1,884 sq ft |
| Concrete | M20 (1:1.5:3) for footings, columns, beams, slabs and stair; 1:3:6 for PCC |
| Steel | Fe500, details as in NBC 205:2024 |
| Walls | 230 mm brick outside, 115 mm inside and parapet |
These are example values. A house on your plot may have different bays, deeper footings or a third storey; use your structural and architectural drawings for the real sizes.
Step-by-step method
Step 1: List the elements
Break the building into items that are built and paid separately: excavation, PCC under footings, footings, columns, beams (plinth, first floor, roof), slabs, staircase, brick walls, plaster, floor PCC and the mortar bed under tiles. Keep this list in the order the work happens on site. It becomes your purchase plan.
Step 2: Take off each element in m3, m2 or kg
Measure each item once and decide where the joints go. In this series the column runs from the top of the footing to the underside of the roof slab, the beams are measured below the slab only, and the slab is measured over its full area. With that rule the beam-column and slab-beam joints are counted once.
Step 3: Convert volumes to materials
For nominal mix concrete use a dry volume factor of 1.54, cement at 1,440 kg/m3 and 50 kg bags. For M20 (1:1.5:3) that gives 1.54 / 5.5 x 1,440 / 50 = 8.06 bags, 0.42 m3 of sand and 0.84 m3 of aggregate per m3. For 1:3:6 it gives 4.44 bags, 0.46 m3 of sand and 0.92 m3 of aggregate per m3. The cement bags for 1 m3 of M20 guide shows the working.
Step 4: Add the steel from the bar schedules
Steel is not a fixed percentage of concrete. Take it from a bar bending schedule for each element, then add wastage once at the end.
Step 5: Add walls and finishes
Bricks, mortar, plaster and tile bedding use a lot of cement but no aggregate. Add them from their own take-offs.
Step 6: Total, add wastage and work out ratios
Add each material across all items, add a small wastage, and divide by the built-up area. The ratio is useful for checking, not for ordering.
Worked example 1: concrete items
The volumes come from the element posts: isolated footing quantity (1.5 x 1.5 m sloped footing, 12 nos), the RCC column, beam and slab examples, and the staircase dimensions post. Two adjustments were made so nothing is counted twice:
- Footings: only the footing itself (0.701 m3 each). The column stub above the footing is already inside the column volume.
- Slabs: the first floor slab loses the 2.1 x 3.2 m stair opening (6.72 m2); the roof slab is full. Each is 125 mm thick.
A 75 mm 1:3:6 PCC sub-floor under the ground floor rooms (77.16 m2 inside area) is added as an example item.
| Item | Volume (m3) | Cement (bags) | Sand (m3) | Aggregate (m3) |
|---|---|---|---|---|
| PCC under footings 1:3:6 (12 x 0.217) | 2.60 | 11.5 | 1.20 | 2.41 |
| Footings M20 (12 x 0.701) | 8.41 | 67.8 | 3.53 | 7.07 |
| Columns M20 (12 nos, footing top to roof) | 10.22 | 82.4 | 4.29 | 8.58 |
| Beams M20 (plinth 5.01 + 3.25 + 3.25) | 11.51 | 92.8 | 4.83 | 9.67 |
| Slabs M20 (80.81 + 87.53 m2 x 0.125) | 21.04 | 169.7 | 8.84 | 17.68 |
| Staircase M20 (two flights + landing) | 1.45 | 11.7 | 0.61 | 1.22 |
| Ground floor PCC 1:3:6, 75 mm | 5.79 | 25.7 | 2.67 | 5.35 |
| Total concrete | 61.02 | 461.6 | 25.98 | 51.96 |
The slab is the single biggest user of cement, about 37% of all the concrete cement. That is why a change in slab thickness from 125 to 150 mm, which some designers use for larger panels, adds about 34 bags to this house on its own (168.34 m2 x 0.025 m x 8.06).
Worked example 2: steel
| Element | Basis | Steel (kg) |
|---|---|---|
| Footing mats | 12 x 29.4 kg (12 mm at 150 c/c both ways) | 352.4 |
| Columns | 12 x 144.8 kg (4-16 + 4-12, 8 mm ties) | 1,737.5 |
| Beams | plinth 548.8 + first floor 630.9 + roof 630.9 | 1,810.6 |
| Slabs | 168.34 m2 x 10.6 kg/m2 (from the slab panel example) | 1,786.0 |
| Total net | 5,686.5 | |
| With 3% wastage | 5,857 |
Net steel is 32.5 kg per m2 of built-up area, or 3.0 kg per sq ft (3.1 with wastage). Column starter bars into the footing and the staircase steel are not in this table; take them from your bar schedule. The steel weight calculator gives the kg per metre for any bar size.
Note the footings: they carry only about 6% of the steel. Columns, beams and slabs share the rest almost equally. If your contractor's steel bill is far above or below this split, ask which element is different and why.
Worked example 3: walls, plaster and floors
| Item | Basis | Cement (bags) | Sand (m3) | Other |
|---|---|---|---|---|
| Brick walls and parapet | 147.83 m2 one-brick 1:6, 94.55 m2 half-brick 1:4 | 57.8 | 10.98 | 24,267 bricks (25,480 with 5%) |
| Plaster | 823.34 m2: outside 20 mm 1:4, inside 12 mm 1:6, ceilings 12 mm 1:4 | 81.7 | 12.90 | |
| Tile bedding and slurry | 181.19 m2 of floor and wall tiles | 37.0 | 3.32 | 431 + 89 + 251 tiles |
| Total | 176.5 | 27.20 |
The details are in the brick wall quantity and plaster quantity posts. Masonry and finishes take about 28% of the cement in this house, which surprises many owners who budget cement only for the frame.
Grand total and ratios
| Material | Total for the house | Per m2 built-up | Per 1,000 sq ft |
|---|---|---|---|
| Cement (50 kg bags) | 638 (670 with 5%) | 3.6 bags | 339 bags |
| Steel (kg, with 3%) | 5,857 | 33.5 kg | 3,108 kg |
| Sand | 53.18 m3 = 1,878 cft | 0.30 m3 | 28.2 m3 |
| Aggregate | 51.96 m3 = 1,835 cft | 0.30 m3 | 27.6 m3 |
| Bricks (with 5%) | 25,480 | 146 | 13,520 |
Sand and aggregate here are dry loose volumes from the mix proportions; add the usual site allowance for bulking of damp sand and for what is lost on the ground. Truck loads in Nepal are often quoted in cft, so 1,878 cft of sand is about 19 loads of 100 cft.
Using the ratios to check a quote
Suppose a contractor offers a 2,400 sq ft, two storey RCC house of a similar layout and lists 1,100 bags of cement and 6,000 kg of steel. From the ratios: 2,400 x 0.34 = about 815 bags and 2,400 x 3.1 = about 7,460 kg of steel. The cement looks high and the steel looks low. That does not prove anything is wrong, but it tells you which questions to ask: is the slab thicker, are there more walls, is the steel figure net of laps? A larger plan with longer spans or a third storey will need more steel per sq ft, so never use the ratio to cut the designer's steel.
Material by stage: what to order and when
Cement goes stale in damp storage, so buy it by stage rather than all at once. For this house the split is:
| Stage | Work | Cement (bags) |
|---|---|---|
| 1 | Footing PCC, footings, columns up to plinth, plinth beams | 134 |
| 2 | Ground floor columns, first floor beams and slab, stair | 153 |
| 3 | First floor columns, roof beams and slab | 149 |
| 4 | Brick walls and parapet | 58 |
| 5 | Plaster inside and outside | 82 |
| 6 | Ground floor PCC and tile bedding | 63 |
| Total | 638 |
In practice the walls of a floor often go up before the next slab is cast, so stages 3 and 4 overlap. Keep each delivery to what can be used within a few weeks, store bags on a raised platform under cover, and use the oldest bags first.

What the structural work costs at municipal rates
Quantities become a budget once you apply rates. The table below uses the Suryabinayak Municipality rate analysis for 2081/82, with the 15% contractor overhead included. These rates cover material, labour and tools for each item.
| Item | Quantity | Rate (Rs) | Amount (Rs) |
|---|---|---|---|
| Excavation, ordinary soil, manual | 79.38 m3 | 529.00 per m3 | 41,992 |
| PCC 1:3:6, manual | 8.39 m3 | 14,655.22 per m3 | 1,22,972 |
| Concrete 1:1.5:3, machine mixed | 52.63 m3 | 17,320.55 per m3 | 9,11,578 |
| Steel work, cut, bend and fix | 5,857 kg | 150.75 per kg | 8,82,957 |
| Formwork, slab (steel prop and plywood) | 137.17 m2 | 923.92 per m2 | 1,26,734 |
| Formwork, beam (steel prop and plywood) | 120.24 m2 | 1,311.65 per m2 | 1,57,713 |
| Formwork, column | 116.76 m2 | 685.17 per m2 | 80,000 |
| Structure total | 23,23,946 |
Slab formwork is the slab area less the beam and column plan areas (2 floors, 137.17 m2); column formwork is 12 x 1.4 m perimeter x 6.95 m. On the same rate analysis the brick walls come to Rs 7,21,737, plaster Rs 4,21,745, tiling Rs 6,67,183 and painting Rs 3,87,325 (see the earlier posts in this series). Together with the structure that is about Rs 45.2 lakh, or about Rs 2,400 per sq ft.
That figure is not the cost of a finished house. It leaves out doors and windows, electrical and plumbing work, sanitary fittings, kitchen, railings, roof waterproofing, the design and permit fees and supervision. Rates also change every fiscal year and differ between municipalities, so use the current rate analysis of your own municipality or district. The house construction cost calculator helps you build a full budget.
What is not included
- Toe walls and the plinth filling under the ground floor PCC.
- Column starter bars, staircase steel and any lintels and sill bands cast separately.
- A stair cover (mumty) on the roof, water tank stands and the septic tank.
- Waterproofing, roof screed and the cement in painting putty.
Add these from your own drawings. On a typical house they add a few per cent to cement and steel.
Common mistakes seen on Nepali sites
- Using one rule of thumb for everything. "0.4 bag per sq ft" or "4 kg of steel per sq ft" may fit one house and be far off for another. Spans, storeys, seismic detailing and wall layout all change the numbers.
- Counting joints twice. If the slab is measured over the full area, beams must be measured below the slab only. On this house, measuring the beams to full depth as well would add about 3.5 m3 of concrete and 28 bags of cement that were never placed.
- Forgetting masonry and plaster cement. Owners who budget only for the frame run short by more than a quarter of their cement.
- Adding wastage at every step. Add it once, on the final total. Wastage on wastage inflates the order by several per cent.
- Buying all the cement at the start. Bags stored through a monsoon lose strength. Order by stage.
- Cutting steel to match a rule. Column and beam steel follow NBC 205 or the design. A low steel ratio is a reason to check the drawings, not a saving.
Frequently asked questions
How many bags of cement for a 1,000 sq ft house in Nepal?
For a two storey RCC house like this one, about 340 bags per 1,000 sq ft of built-up area, including walls, plaster and tile bedding. A single storey house needs more per sq ft because the footings and roof are spread over less floor area.
How much steel per sq ft for an RCC house in Nepal?
This example gives 3.0 kg per sq ft net and 3.1 kg with wastage. Houses with longer spans, cantilevers or more storeys need more. Always take steel from the bar schedule; our engineering tools include calculators for each element.
Why is the slab such a large part of the concrete?
A 125 mm slab over 168 m2 is 21 m3, more than the columns and beams combined above plinth. Slab thickness is the first thing to check when a concrete quantity looks high.
Do these numbers follow the Nepal building code?
The member sizes and reinforcement follow the examples in NBC 205:2024, the ready-to-use detailing guideline for RC buildings, with checks against IS 456:2000. Your municipality may require an engineered design for your house, and that design governs.
Can I use this for a three storey house?
Use the method, not the totals. Column and beam steel rise with each storey and the footings grow, so redo each element from your drawings.