Staircase Steel Quantity in Nepal: Dog-Legged Stair BBS Example

Cover: bar bending schedule for a dog-legged RCC staircase with waist slab bars

A dog-legged RCC stair for a 3.0 m storey in a Nepali house, 1.0 m wide with a 150 mm waist slab, 12 mm main bars at 150 mm and 8 mm distribution bars at 200 mm, needs about 142 kg of steel net, or about 147 kg with 3% for laps and cutting waste. That is roughly 120 kg of 12 mm bar and 23 kg of 8 mm bar, bought as about 13 lengths of 12 mm and 6 lengths of 8 mm (12 m bars). For each m3 of stair concrete it works out to about 98 kg of steel. This guide shows how to build the bar bending schedule (BBS) for the stair, bar by bar, so you can check a contractor's figure or order steel for your own house.

The stair is the same one used in our staircase dimensions guide: 18 risers of 166.7 mm, treads of 275 mm, two flights of 9 risers with a half landing of 2.1 x 1.0 m. The bar sizes come from the Nepal code for small houses; the spacings and anchorage are example values that you should replace with the ones on your structural drawing.

What the codes say about stair steel

NBC 205:2024, the Nepal building code for low-rise reinforced concrete buildings, gives a stair waist slab of 150 mm (6 inch) with 12 mm longitudinal bars and 8 mm distribution bars, and shows the layout in its staircase figures (Figures 10-4 and 10-5). The same code makes the walls around the staircase 9 inch brick, uses dedicated staircase columns that enclose the stair, and its beam tables give the stair cover beams as 250 x 355 mm with 3 bars of 12 mm top and bottom. Read the spacing straight from the figure in the code or from your structural drawing. In this article we use 12 mm at 150 mm and 8 mm at 200 mm as example spacings and then check them against IS 456 below.

IS 456:2000, which Nepali designers also use for RC design and detailing, treats a waist slab as a slab spanning along the slope. The checks that matter for the BBS are:

  • Minimum steel in each direction: 0.12% of the gross section for Fe 415 and Fe 500 bars (clause 26.5.2.1).
  • Maximum spacing of main bars: 3d or 300 mm, whichever is less; distribution bars: 5d or 450 mm (clause 26.3.3).
  • Largest bar: not more than one eighth of the slab thickness, so 18.75 mm for a 150 mm waist.
  • Clear cover: 20 mm for mild exposure, 30 mm for moderate exposure (Table 16). Stairs inside a house are usually mild; an open stair to the terrace is better treated as moderate.
  • Effective span of a flight that spans between landings: the going plus, at each end, half the landing width or 1 m, whichever is less (clause 33.1).

Check of the example spacings

Effective depth d = 150 - 20 - 6 = 124 mm. Main steel 12 mm at 150 mm = 754 mm2 per metre = 0.50% of 150 mm, which is well above 0.12%, and 150 mm is less than 3d (372 mm) and 300 mm. Distribution steel 8 mm at 200 mm = 251 mm2 per metre = 0.17%, above the 0.12% minimum (180 mm2), and 200 mm is less than 450 mm. A 12 mm bar is below the 18.75 mm limit. The spacings pass the detailing rules; whether they carry the load is a design question for your engineer.

Development length

For Fe 500 bars in M20 concrete the IS 456 development length is 0.87 x 500 x d / (4 x 1.92) = 56.6 d, which matches the 57 d lap length that NBC 205 uses for beams and columns. For a 12 mm bar that is 57 x 12 = 684 mm. We use this length wherever a bar must anchor into a support or cross into the landing.

Reinforcement in one flight and the landing of a dog-legged stair Section through a stair flight rising from a floor beam to a half landing. Bottom main bars a run along the waist slab and cross into the top of the landing by a development length. Landing bars e run along the landing bottom and cross down into the top of the waist. Top bars b sit at both ends of the flight. Distribution bars c and d are shown as dots. floor beam landingbeam/wall a 12 mm @ 150 bottom b 12 mm @ 150 top (0.3 x flight + Ld, both ends) c, d 8 mm @ 200 distribution e landing 12 @ 150 Ld = 57d = 684 mm waist 150 mm 9 risers 166.7 mm, 8 treads 275 mm, going 2.2 m How to schedule Inclined length = going x 1.169 = 2.573 m Bar a = 2.573 + 2 x 0.684 = 3.941 m Number = width less cover / spacing + 1 = 8 per flight kg = m x d2/162
One flight and the half landing. Bottom bars a cross into the top of the landing, landing bars e cross into the top of the waist, so neither bar is bent around the inside corner. Spacings are example values.

How to make a staircase BBS: step-by-step method

  1. Fix the geometry. Note the riser R, tread T, treads per flight, flight width, waist thickness and landing size from the drawing. Here R = 166.7 mm, T = 275 mm, 8 treads per flight, width 1.0 m, waist 150 mm, landing 2.1 x 1.0 m.
  2. Find the inclined length of the flight. Going = 8 x 0.275 = 2.2 m. Slope factor = square root of (1 + (R / T) squared) = square root of (1 + 0.606 squared) = 1.169. Inclined length = 2.2 x 1.169 = 2.573 m.
  3. List every bar type. For a waist slab stair: bottom main bars, top bars at the supports, distribution bars under each layer, landing main bars and landing distribution bars. Give each one a mark (a, b, c ...).
  4. Work out the cut length. Cut length = clear length inside the cover + anchorage at each end. Bottom main bar a = 2.573 + 2 x 0.684 = 3.941 m.
  5. Count the bars. Number = (width - 2 x cover) / spacing, rounded up, + 1. For main bars across a 1.0 m flight: (1000 - 40) / 150 = 6.4, round up to 7 spaces, so 8 bars. Distribution bars along the slope: 2.573 / 0.2 = 12.9, so 13 spaces and 14 bars.
  6. Weigh it. kg = total length x d2 / 162. A 12 mm bar weighs 0.889 kg/m and an 8 mm bar 0.395 kg/m (see the D2/162 formula).
  7. Multiply for both flights, add the landing and add 3% for laps and waste.
  8. Plan the cutting from 12 m bars so offcuts are used, and order whole bars.

Worked example 1: BBS for a dog-legged stair (3.0 m storey)

Assumptions: two flights, each 1.0 m wide, 150 mm waist, 20 mm cover. Main and landing bars 12 mm at 150 mm; distribution 8 mm at 200 mm. Top bars at both ends of each flight run 0.3 of the inclined length (0.772 m) plus 684 mm anchorage = 1.456 m. Landing main bars run in the direction of the flights: 1.0 - 0.04 + 0.684 anchorage into the landing beam or wall = 1.644 m. Bends at the kink are counted as straight length; the bend deduction is small and ignoring it errs on the safe side.

MarkBarDia (mm)NumberCut length (m)Total length (m)Weight (kg)
aBottom main, along the flight (2 flights x 8)12163.94163.0556.04
bTop bars, both ends of each flight (2 x 2 x 8)12321.45646.5841.41
cDistribution under bottom bars (2 x 14)8280.96026.8810.62
dDistribution under top bars (2 x 2 x 5)8200.96019.207.59
eLanding main, 2.1 m landing12151.64424.6621.92
fLanding distribution862.06012.364.88
Total net (12 mm 119.37 kg, 8 mm 23.09 kg)142.46
With 3% for laps and waste146.7

The concrete in the same stair is 1.45 m3 (two waist slabs 0.386 m3 each, steps 0.183 m3 each and the landing 0.315 m3), so the steel ratio is 142.46 / 1.45 = about 98 kg per m3. That is lower than a column (about 170 kg per m3 in our column example) because the triangular steps add concrete but no steel.

Cutting plan from 12 m bars

  • Bar a, 3.941 m: 3 pieces per 12 m bar (11.82 m used). 16 pieces need 6 bars.
  • Bar b, 1.456 m: 8 pieces per bar (11.65 m). 32 pieces need 4 bars.
  • Bar e, 1.644 m: 7 pieces per bar (11.51 m). 15 pieces need 3 bars, with offcuts left over.
  • Bars c and d, 0.96 m: 12 pieces per 8 mm bar. 48 pieces need 4 bars. Bar f, 2.06 m: 5 per bar, so 2 bars.

So order 13 bars of 12 mm (13 x 10.67 = 138.7 kg) and 6 bars of 8 mm (6 x 4.74 = 28.4 kg), about 167 kg in all. The 25 kg above the net figure is offcut, which goes into chair bars, lintels or the next stair. You can check any line of this schedule with the steel weight calculator.

Worked example 2: cost of the whole stair

Using the Suryabinayak Municipality rate analysis for 2081/82 (rates include 15% overhead), the same rates our whole-house cement and steel summary used:

ItemQuantityRate (Rs)Amount (Rs)
Machine-mixed concrete 1:1.5:3 (M20)1.45 m317,320.55 per m325,115
Steel work (cutting, bending, fixing)146.7 kg150.75 per kg22,120
Formwork with steel props and ply (slab rate used)12.76 m2923.92 per m211,789
Structure of one stair59,024

That is about Rs 3,300 per riser before tiles, handrail and plaster. The 12.76 m2 of formwork comes from our formwork quantity guide, and the concrete from the stair dimensions post. The whole-house summary counted the stair concrete but not its steel, so add about 147 kg to that house's steel order.

Quick table: stair steel for other sizes

Same method, same bars and spacings, tread 275 mm, landing length = 2 x width + 0.1 m. Dog-legged stairs with two equal flights.

Floor heightWidthRisersConcrete (m3)Steel net (kg)With 3% (kg)kg per m3
2.85 m0.9 m18 x 158.3 mm1.26124.5128.399
2.85 m1.0 m18 x 158.3 mm1.42141.7145.999
2.85 m1.2 m18 x 158.3 mm1.78167.1172.194
3.0 m0.9 m18 x 166.7 mm1.28125.2129.098
3.0 m1.0 m18 x 166.7 mm1.45142.5146.798
3.0 m1.2 m18 x 166.7 mm1.82167.9173.093
3.2 m0.9 m20 x 160.0 mm1.39133.7137.797
3.2 m1.0 m20 x 160.0 mm1.57152.1156.797
3.2 m1.2 m20 x 160.0 mm1.96179.0184.492

For a 2.5-storey house with a stair to the terrace, multiply by the number of stairs: three 3.2 m stairs of 1.0 m width need about 3 x 157 = 470 kg. A 2.85 m storey with 18 risers and a 275 mm tread gives 2R + T of only 592 mm; a 290 mm tread is more comfortable and adds a little steel.

Bent reinforcement bars of a bridge foundation on site at Bhadrapur, Nepal
Bent and hooked bars on a Nepali site: every bend and hook on the drawing must appear in the schedule as cut length. Photo: Bridge Reinforcement by Wonaw, CC BY-SA 3.0, via Wikimedia Commons (Mechi Bridge foundation, Bhadrapur)

Common mistakes on Nepali house sites

  • Bending the bottom bars around the inside corner. At the junction of flight and landing the bottom bars are often bent to follow the soffit. Under load such a bar tries to straighten and pushes off the cover. Cross the bars instead: flight bars into the top of the landing, landing bars into the top of the waist, each by a development length.
  • Measuring bars on the going instead of the slope. Using 2.2 m instead of 2.573 m cuts 0.37 m (15%) from the sloping part of every main bar and leaves the schedule about 10 kg light for this stair.
  • No top steel at the supports. Many site stairs have only one bottom mesh. Where the flight is built into a beam or wall, it cracks on top near the support. Follow the top bars on the drawing.
  • Waist thinner than drawn. The waist is measured at right angles to the soffit, not vertically. A 150 mm vertical thickness is only 128 mm perpendicular on this slope.
  • Bars resting on the shuttering. Without 20 mm cover blocks the bottom bars rust from below within a few years. Tie cover blocks at about 1 m spacing and chair the top bars.
  • Casting the flight without the starter bars for the next flight or landing. Leave the landing bars and the anchorage lengths projecting at construction joints, and do not stop a pour at the kink.
  • Counting bar numbers as width / spacing. Always add one: 960 / 150 gives 7 spaces and 8 bars, not 6 or 7.

Frequently asked questions

How much steel is needed for a staircase in a house in Nepal?

For a 1.0 m wide dog-legged stair with a 150 mm waist and a 3.0 m storey, about 140 to 150 kg per stair. Wider stairs, taller storeys and heavier bars on the drawing raise it; see the table above.

How much steel per m3 of stair concrete?

About 90 to 100 kg per m3 with 12 mm at 150 mm and 8 mm at 200 mm. Use it only as a check on an estimate, never in place of a schedule.

Do the steps need reinforcement?

Steps cast together with a waist slab are usually plain concrete. Some designers add a nosing bar in each step to control cracking; if your drawing shows one, add 1 bar per step to the schedule.

Which bar goes on top at the landing junction?

Follow the drawing. The usual rule is that each bar that is in tension on the outside of the bend is carried past the corner into the compression zone of the other element by its anchorage length.

Can I use 10 mm bars instead of 12 mm?

Only if your engineer revises the spacing. 10 mm bars at 150 mm give 524 mm2 per metre against 754 for 12 mm, a 30% cut in steel area.

Is the BBS for a stair different from a beam BBS?

The method is the same: cut length, number of bars and weight. See the bar bending schedule for a beam for hooks and bend deductions, and the RCC slab quantity example for slab bars.

Sources

Bar sizes, spacings and rates in this article are for estimating. Your structural drawing, your municipality's bylaws and the current year's rates take priority. Use the stair calculator for risers and concrete, practise RCC detailing questions in the free engineering MCQ practice, and find more calculators on the engineering tools page.

Preparing for the NEC licence or Lok Sewa?Practise 2,100+ civil engineering MCQs with answers, free.Start practising

Comments

Need a calculator we don’t have yet?

Tell us what you use on site or in class. The most requested tools get built next.